Misplaced Pages

Connaught Tunnel

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

The Connaught Tunnel is in southeastern British Columbia , on the Revelstoke – Donald segment. The 5.022-mile (8.082 km) tunnel carries the Canadian Pacific Kansas City (CPKC) main line under Mount Macdonald in the Selkirk Mountains . The tunnel, opened by the Canadian Pacific Railway (CP) in 1916, replaced the previous routing over Rogers Pass .

#129870

40-529: Traffic restrictions imposed by a single track comprising 46 miles (74 km) of 2.2 percent gradients, emerging competition, and snow-related costs, were negative factors. The 1910 Rogers Pass avalanche , and other avalanches on the pass, influenced but did not unduly pressure CP to consider alternatives; however, snow clearing and maintaining snow sheds was an ongoing burden. Rarely assigning more than one pusher locomotive per train, trains over 1,016 tons had to be cut. Higher capacity locomotives had helped, but

80-404: A different calculation of $ 8.45M. In all, the route was shortened by 4.3 miles (6.9 km). In 1919, 30 drums of gasoline and kerosene, used by the concrete mixers engaged in the lining operation, ignited. A tunnel watchman, who rushed some distance to the nearest telephone to alert Connaught station at the eastern portal, did not survive. His warning saved the westbound transcontinental, then at

120-522: A locomotive boiler explosion killed three crew members near Glacier. In 1929, two train crew died when their locomotive fell into the ravine when a girder collapsed on the Surprise Creek Bridge. The 1931 flood sent 2,000 replacement ties through the tunnel and filled the west portal cutting to a 20-foot (6.1 m) depth with 10,000 to 12,000 cubic yards (7,600 to 9,200 m) of mud and debris, which took five days to dig out. Approved in 1958,

160-455: A mission to clear the tracks and recover the bodies beneath 10 metres of snow. Many of the dead were found standing upright, frozen in position, reminiscent of Pompeii . 58 workers were killed. Among the dead were 32 Japanese workers. The disaster was not the first to befall the pass; in all over 200 people had been killed by avalanches there since the line was opened 26 years previously. The CPR finally accepted defeat and in 1913 began boring

200-460: A pioneer tunnel advanced from each end, from which cross cuts were made to the main tunnel so work could carry on at a number of headings simultaneously. Compressed air equipment, blasting, steam shovels, and narrow-gauge cars were used. At 23 feet (7.0 m) high and 29 feet (8.8 m) wide, the tunnel would accommodate double tracks . The western side involved penetrating thick mud, extremely hard rock, and finally softer rock. The highest point of

240-513: A snow shed. The crew sustained minor injuries. The line remained closed for a week. In 1985, a nearby rock slide derailed one of the four locomotives hauling a coal train. The tunnel was deepened to clearances matched with the Mount Macdonald Tunnel in 1993 to accommodate double-stack container cars with future electrification. This first 24/7 work project undertaken by CP was a significant engineering challenge. In 1997, eight cars of

280-406: A train derailed in the vicinity. In 2015, six cars of a westbound freight derailed on Stoney Creek Bridge. The train had diverted to the eastbound route because the Mount Macdonald Tunnel was being vented. The incident occurred when the train lost momentum on the steeper grade and stopped with the cars on the bridge. However, restarting on the curve caused the heavier cars at the front and rear of

320-701: Is often used when performance, quality or delivery time is a much greater concern than cost, such as in the United States space program . Cost plus contracting was expanded to include services such as engineering, consulting, and a variety of other such efforts in the 1980's. Between 1995 and 2001 fixed fee cost-plus contracts constituted the largest subgroup of cost-plus contracting in the U.S. defense sector. Starting during 2002 award-fee cost plus contracts became more numerous than fixed fee cost plus contracts. The distribution of annual contract values by sector category and award types indicates that cost plus contracts in

360-567: The Illecillewaet River for about 1 mile (1.6 km). Let out to tender in April 1913, the bids received were unacceptably high. It was immediately retendered as a cost-plus contract , with bonus and penalty clauses . After negotiations with the lowest bidder, the contract was awarded to Foley, Welch and Stewart (FW&S) in July 1913. The Rogers Pass article shows the summit route details. Only

400-568: The Selkirk Mountains in British Columbia on March 4, 1910. It is Canada 's worst avalanche disaster. The Canadian Pacific Railway 's line through Rogers Pass completed its transcontinental railroad through to Canada's west coast, and at the time was the only such link. It was therefore of vital importance to keep it open through the winter months. Although completed in November 1885 it

440-508: The 1920s. To improve visibility on the 1929 introduction of the Selkirk locomotives , trains switched to the left-hand track before entering the tunnel. In 1950, multiple aspect signalling was installed. In 1954, diesel locomotives became standard. Pusher units cut into westbound freight trains at Beavermouth, before disconnecting at Stoney Creek. On occasions, when pushers worked through to Glacier, crew were required to wear respirators, owing to

SECTION 10

#1732837597130

480-544: The Selkirks track was just inside the western portal. Three steam shovels were based on the west side and one on the east. Death and injury were not uncommon. Mirroring the advance across the pass in the 1880s, concern for the health and safety of workers was not a priority. Beating world monthly tunneling records, the pioneer headings met in December 1915, and the main bores in July 1916. The unacceptably high cost projection scrapped

520-548: The Yellowhead to Vancouver , the premier destination, prompted greater alarm. The opening of the Panama Canal , which bypassed all North American rail routes, offered some compensation in that grain traffic destined for Europe could travel westward by rail. In 1902, the 7-mile (11 km) Ottertail Diversion, west from Field , eliminated the need for pushers. In 1887, after a 500-foot (150 m) tunnel collapsed near Palliser ,

560-412: The bridges at Mountain, Surprise, and Stoney creeks. The tunnel was completed 11 months ahead of schedule and below budget. One calculation of costs listed tunneling $ 4.91M, tunnel track $ 0.16M, approaches $ 0.86M, and ventilation $ 0.11M, totaling $ 6.04M, less the salvage value of the abandoned line $ 1.67M. Extending the concrete lining during 1919–1925 added a further $ 2.60M. The $ 8.64M total is in line with

600-478: The contractor is paid a negotiated amount regardless of incurred expenses. Frank B. Gilbreth , one of the early developers of industrial engineering, used "cost-plus-a-fixed sum" contracts for his building contracting business. He described this method in an article in Industrial Magazine in 1907, comparing it to fixed price and guaranteed maximum price methods. Cost-plus contracts were first used by

640-445: The contractor, plus a fee or profit which differs by contract type. A cost-reimbursement contract is appropriate when it is desirable to shift some risk of successful contract performance from the contractor to the buyer. It is used most commonly when the item purchased cannot be defined explicitly, as for research and development , or for cases where there is not enough data to estimate the final cost accurately. A cost-plus contract

680-605: The crest and eastern slope of the tunnel route is underground. The primary construction camp was near the western portal, a secondary one was near the eastern portal, and a minor one was at Bear Creek. The western portal one, housing 300, was approached either from Loop Spur or the government road from Glacier House . The eastern portal one, housing 200, had only rail access. Both comprised a police post, small hospital, general store, offices, apartments, bunkhouses, kitchen, dining hall, and lounge, with electric lighting and plumbing for water and sanitation. Operating three shifts daily,

720-408: The curves at Illecillewaet. On hearing the radio message, a 60-car eastbound freight accelerated to safely reach Illecillewaet siding (Mile 98.1), before three crew members stepped clear of their train. The runaway's three lead locomotives, 45 cars, a remote control locomotive , and the following 22 cars, were destroyed on derailing at Mile 94.4. The impact shifted a bridge from its footings and damaged

760-572: The east slope and 6.2 miles (10.0 km) on the west one. John G. Sullivan, chief engineer, recommended a 5.3-mile (8.5 km) tunnel, similar to, but more expensive than, the Busteed one. All proposals eliminated the Loops on the west slope of the pass route . The stated advantages were three-fold. Primarily, the tunnel lowered the grade; secondly, it shortened the distance; and thirdly, it bypassed an avalanche-prone zone. The specified alignment would lower

800-420: The electrification plan. Instead, ventilation fans were installed. East of the tunnel, the plan for double-tracking to Six-Mile Creek was amended to a level 2.8-mile (4.5 km) single track connecting with the existing line at Stoney Creek. This reduced the pusher gradient on the east slope by 7.2 miles (11.6 km), 2.4 miles (3.9 km) less than specified. However, it retained the substantial investment in

840-530: The five mile long Connaught Tunnel through Mount Macdonald , at the time Canada's longest tunnel, so bypassing the hazard of Rogers Pass. It was opened on December 13, 1916, and the railway abandoned the pass. Cost-plus contract A cost-plus contract , also termed a cost plus contract , is a contract such that a contractor is paid for all of its allowed expenses, plus additional payment to allow for risk and incentive sharing. Cost-reimbursement contracts contrast with fixed-price contract , in which

SECTION 20

#1732837597130

880-473: The following year a single track down the center (replacing the double tracks) provided sufficient clearance for tri-deck automobile carriers . In 1972 and 1976, the tunnel fans and housing sustained extensive damage on catching fire. In 1977, soon after departing the Glacier siding (Mile 85.9), a westbound loaded 109-car coal train lost control, and broadcast a warning that they were travelling too fast to make

920-529: The former had priority, causing siding waits for the latter. The opening of the Grand Trunk Pacific (GTP) posed a threat to CP's grain and Asian trade. Using a single locomotive, GTP could haul 2,041 tons from Edmonton to Prince Rupert , via Yellowhead Pass , four times the weight CP could haul across the mountains on its main line. The opening of the Canadian Northern Railway (CNoR) via

960-778: The government in the United States during World War I to encourage wartime production by American businesses. According to Martin Kenney, they "allowed what were then small technology firms like Hewlett-Packard and Fairchild Semiconductor to charge the Department of Defense for the price of research and development that none could pay on its own. This enabled the firms to create technology products that eventually created entire new markets and economic sectors". There are four general types of cost-reimbursement contracts, all of which pay every allowable, allocatable, and reasonable cost incurred by

1000-440: The locomotive were crushed and all but one of the workmen were instantly buried in the deep snow. The only survivor was locomotive fireman Billy Lachance, who had been knocked over by the wind accompanying the fall but otherwise remained unscathed. When news of the disaster reached nearby Revelstoke a relief train consisting of 200 railmen, physicians and nurses was sent to the scene. They found no casualties to treat; it became

1040-531: The next leap forward would not occur until the Selkirk locomotives emerged in 1929. In 1912, the average of eight trains (peaking at 11) per day in each direction was forecast to double over the next four years. The program to double-track much of the route through the mountains could create a bottleneck at Rogers Pass. Following the 1906–1908 recession, by 1912, passenger and freight volumes surpassed records. Whereas passenger train length could increase, freight could not, because of weight capacity limits. Furthermore,

1080-590: The past had the largest importance in research, followed by services and products. In 2004, however, services replaced research as the dominant sector category for cost-plus contracts. For all other contract types combined the relative ranking is reversed to the original cost-plus order, meaning that products are most numerous, followed by service and research. With cost-plus contracting being designed primarily for research and development, cost plus contracts were used in many different efforts unrelated to research and development. The percentage of cost-plus contracting within

1120-401: The station, from proceeding into the tunnel. Nine workers escaped on a handcar from the east portal, and one watchman staggered from the west portal. To deal with crumbling rock in the roof, the concrete tunnel lining was extended from 7,837 feet (2,389 m) to 26,512 feet (8,081 m). Prior to the 1925 completion of the project, falling rock killed or injured several workers. In 1928,

1160-500: The summit. Three schemes were considered. In 1912, Thomas Kilpatrick, superintendent of the Mountain Subdivision, suggested a 7-mile (11 km) tunnel, which would have shortened the line by 4.4 miles (7.1 km), reducing the pusher gradient by 13.8 miles (22.2 km) on the east slope and 6.9 miles (11.1 km) on the west one. This alignment would have eliminated the bridges at Mountain, Surprise, and Stoney creeks, but

1200-678: The temporary realignment around a bluff of the Kicking Horse River existed until the 694-foot (212 m) Palliser Tunnel (1906). In 1909, the Spiral Tunnels replaced the Big Hill . The three basic options within the Selkirks were to use the Big Bend, double-track the summit, or dig a tunnel. The Big Bend route was not a viable contender. Estimates indicated that a tunnel would be cheaper than snow sheds and operational costs for double-tracking

1240-473: The time, this was the largest single judgement obtained in a BC court. W.J. Hackman (1928–1953) was the first child born in the tunnel. The birth occurred on the westbound CP No. 2. Passenger train. The next birth appears to have occurred in 1939. 1910 Rogers Pass avalanche The 1910 Rogers Pass Avalanche killed 58 men clearing a railroad line just outside of Revelstoke in Rogers Pass through

Connaught Tunnel - Misplaced Pages Continue

1280-449: The track summit from 4,342 feet (1,323 m) to 3,794 feet (1,156 m), shorten the line by 4.4 miles (7.1 km), reduce the pusher gradient by 9.6 miles (15.4 km) on the east slope and 5.9 miles (9.5 km) on the west one, and eliminate the Stoney, Surprise, and Mountain creek bridges. The tunnel grade would be 0.95% westward. At the west portal, the route required a diversion of

1320-506: The track. The winter of 1909–1910 provided conditions particularly conducive to avalanches; many slides being experienced during January and February. On March 1, 96 people had been killed further south in the Wellington avalanche in Washington state . Three days later on the evening of March 4 work crews were dispatched to clear a big slide which had fallen from Cheops Mountain , and buried

1360-635: The tracks just south of Shed 17. The crew consisted of a locomotive-driven rotary snowplow and 63 men. Time was critical as westbound CPR Train Number 97 was just entering the Rocky Mountains , bound for Vancouver . Half an hour before midnight as the track was nearly clear, an unexpected avalanche from Avalanche Mountain swept down the opposite side of the track to the first fall. Around 400 metres of track were buried. The 91-ton locomotive and plow were hurled 15 metres to land upside-down. The wooden cars behind

1400-401: The train to lift the lighter middle cars from the track. The first commercial train was December 1916, which traveled via Loop Spur, since the pass line remained in use until a few days later. The most northern part of the Loops between the two hillsides, which had been a long trestle, but likely infilled around 1906, needed to be breached by the new line. Automatic block signalling came in

1440-612: The tunnel fumes. The tunnel blocked radio communication. The 1974 realignment west of Beavermouth moved the connection point to Rogers. After the 1988 opening of the Mount Macdonald Tunnel, westbound traffic primarily used that lower gradient route, with Connaught handling eastbound. During the pusher station's existence, six engineers, six maintenance workers, and nine locomotives were based at Rogers. Five-engine units were used on heavy trains carrying grain, coal, and potash. Four-engine units were used on other freights. When opened,

1480-764: The tunnel ranked eighth in length: However, it took the title from the Hoosac Tunnel (1875) 7.64 km (4.75 mi) as the longest railway tunnel in North America until displaced by the Moffat Tunnel (1928) 10.0 km (6.2 mi) in 1928. Officially opened in July 1916 by the Prince Arthur, Duke of Connaught , the governor general, the Selkirk Tunnel was renamed the Connaught Tunnel weeks later. In 2001,

1520-626: The tunnel was inducted into the North America Railway Hall of Fame. When partway through the project, rock drillers J. A. McIlwee and Sons encountered an unexpected predominance of crumbly slate, FW&S dismissed the subcontractor, rather than negotiate a contract variance. After several appeals, including a hearing of the Judicial Committee of the Privy Council , the courts awarded McIlwee about $ 576,000 for breach of contract. At

1560-480: Was rejected owing to perceived construction deadlines, and a route beneath the headwaters of the Illecillewaet River , vulnerable to leakage. The deadline and route fears proved suspect. F.F. Busteed, general superintendent of the Pacific Division, proposed a 5.17-mile (8.32 km) tunnel, which would have shortened the line by 3 miles (4.8 km), reducing the pusher gradient by 10.8 miles (17.4 km) on

1600-416: Was soon abandoned as throughout that winter, up to 12 metres of snow buried the line and avalanches tore away newly-laid sections of track. A costly system of 31 ' snow sheds ' was constructed to protect the most vulnerable sections of line, covering 6.5 km (4.0 mi) in all. However, most of the route through the pass was still unprotected, meaning that men and equipment were often called upon to clear

#129870