Communications-based train control ( CBTC ) is a railway signaling system that uses telecommunications between the train and track equipment for traffic management and infrastructure control. CBTC allows a train's position to be known more accurately than with traditional signaling systems. This can make railway traffic management safer and more efficient. Rapid transit system (and other railway systems) are able to reduce headways while maintaining or even improving safety.

#52947

89-466: A CBTC system is a "continuous, automatic train control system utilizing high-resolution train location determination, independent from track circuits ; continuous, high-capacity, bidirectional train-to-wayside data communications; and trainborne and wayside processors capable of implementing automatic train protection (ATP) functions, as well as optional automatic train operation (ATO) and automatic train supervision ( ATS ) functions," as defined in

178-413: A moving block system as shown in the second figure, the train position and its braking curve is continuously calculated by the trains, and then communicated via radio to the wayside equipment. Thus, the wayside equipment is able to establish protected areas, each one called Limit of Movement Authority (LMA), up to the nearest obstacle (in the figure the tail of the train in front). Movement Authority (MA)

267-409: A Frequency Spectrum for Critical Safety Applications dedicated to Urban Rail Systems) to reserve a frequency band specifically for radio-based urban rail systems. Such decision would help standardize CBTC systems across the market (a growing demand from most operators) and ensure availability for those critical systems. As a CBTC system is required to have high availability and particularly, allow for

356-547: A Level 2-equipped train. A route is locked based on the national principles by the interlocking system and the RBC is informed about the routes set. The RBC checks whether it is possible to allocate a train to the route and then informs the interlocking system that a train is allocated to the route. The interlocking system may show the ETCS white bar aspect to signals at the ETCS Border or along

445-488: A better adaptation of the transport offer to the actual demand, allows significant energy savings reducing the power consumption. The primary risk of an electronic train control system is that if the communications link between any of the trains is disrupted then all or part of the system might have to enter a failsafe state until the problem is remedied. Depending on the severity of the communication loss, this state can range from vehicles temporarily reducing speed, coming to

534-418: A brake application to reduce speed a penalty brake application is made automatically. Due to the more sensitive handling and control issues with North American freight trains, ATC is almost exclusively applied to passenger locomotives in both inter-city and commuter service with freight trains making use of cab signals without speed control. Some high-volume passenger railroads such as Amtrak , Metro North and

623-507: A careful analysis of the benefits and risks of a given CBTC architecture (centralized vs. distributed) must be done during system design. When CBTC is applied to systems that previously ran under complete human control with operators working on sight it may actually result in a reduction in capacity (albeit with an increase in safety). This is because CBTC operates with less positional certainty than human sight and also with greater margins for error as worst-case train parameters are applied for

712-528: A development plan first mentioned the creation of the European Rail Traffic Management System . In 1996 the first specification for ETCS followed in response to EU Council Directive 96/48/EC99 on interoperability of the trans-European high-speed rail system . The functional specification of ETCS was announced In April 2000 as guidelines for implementation in Madrid . In autumn 2000

801-539: A fully redundant architecture of the CBTC system may however achieve high availability values by itself. In principle, CBTC systems may be designed with centralized supervision systems in order to improve maintainability and reduce installation costs. If so, there is an increased risk of a single point of failure that could disrupt service over an entire system or line. Fixed block systems usually work with distributed logic that are normally more resistant to such outages. Therefore,

890-416: A graceful degradation, a secondary method of signaling might be provided to ensure some level of non-degraded service upon partial or complete CBTC unavailability. This is particularly relevant for brownfield implementations (lines with an already existing signalling system) where the infrastructure design cannot be controlled and coexistence with legacy systems is required, at least, temporarily. For example,

979-572: A halt or operating in a degraded mode until communications are re-established. If communication outage is permanent some sort of contingency operation must be implemented which may consist of manual operation using absolute block or, in the worst case, the substitution of an alternative form of transportation . As a result, high availability of CBTC systems is crucial for proper operation, especially if such systems are used to increase transport capacity and reduce headway. System redundancy and recovery mechanisms must then be thoroughly checked to achieve

SECTION 10

#1732852484053

1068-509: A high robustness in operation. With the increased availability of the CBTC system, there is also a need for extensive training and periodical refresh of system operators on the recovery procedures . In fact, one of the major system hazards in CBTC systems is the probability of human error and improper application of recovery procedures if the system becomes unavailable. Communications failures can result from equipment malfunction, electromagnetic interference , weak signal strength or saturation of

1157-470: A more severe penalty application that will bring the train to a stop. Neither system requires explicit speed control or adherence to a braking curve . The Union Pacific system requires an immediate brake application that cannot be released until the train's speed has been reduced to 40 mph (64 km/h) (for any train traveling above that speed). Then, the train's speed must be further reduced to no more than 20 mph (32 km/h) within 70 seconds of

1246-425: A route currently assigned for optical authorisation (e.g. after Start Of Mission (SOM) procedure or when the driver changes level from Level NTC to Level 2), the optical authorisation is automatically upgraded to a Level 2 movement authority. Consequently, a Level 2 movement authority is downgraded to an optical authorisation after a predefined time-out if the driver closes the cab or a fault is detected that restricts

1335-731: A variety of applications as shown in the figure below (mid 2011). They range from some implementations with short track, limited numbers of vehicles and few operating modes (such as the airport APMs in San Francisco or Washington ), to complex overlays on existing railway networks carrying more than a million passengers each day and with more than 100 trains (such as lines 1 and 6 in Madrid Metro , line 3 in Shenzhen Metro , some lines in Paris Metro , New York City Subway and Beijing Subway , or

1424-414: Is a general class of train protection systems for railways that involves a speed control mechanism in response to external inputs. For example, a system could effect an emergency brake application if the driver does not react to a signal at danger. ATC systems tend to integrate various cab signalling technologies and they use more granular deceleration patterns in lieu of the rigid stops encountered with

1513-489: Is also planned to be used on the soon to open Line 5 Eglinton line, however, Unlike on Line 1, the system on Line 5 will be supplied by Bombardier Transportation using its Cityflo 650 technology. The TTC plans to convert Line 2 Bloor-Danforth and Line 4 Sheppard to ATC in the future, subject to funding availability and being able to replace the current non-ATC compatible fleet on Line 2 with trains that are, with an estimated date of completion by 2030. ATC systems in

1602-410: Is compared with the speed limit and the brakes are applied automatically if the train is travelling too fast. The brakes are released as soon as the train slows below the speed limit. This system offers a higher degree of safety, preventing collisions that might be caused by driver error, so it has also been installed in heavily used lines, such as Tokyo's Yamanote Line and some subway lines. Although

1691-472: Is considered as a basic enabler technology for this purpose. There are four grades of automation available: CBTC systems allow optimal use of the railway infrastructure as well as achieving maximum capacity and minimum headway between operating trains, while maintaining the safety requirements. These systems are suitable for the new highly demanding urban lines, but also to be overlaid on existing lines in order to improve their performance. Of course, in

1780-602: Is different from that of its neighbours. From 1978 until 1987, the Swedish ATC system was trialled in Denmark, and a new Siemens -designed ATC system was implemented between 1986 and 1988. In consequence of the Sorø railway accident , which occurred in April 1988, the new system was progressively installed on all Danish main lines from the early 1990s onwards. Some trains (such as those employed on

1869-474: Is done by replacing former national signalling equipment and operational procedures with a single new Europe-wide standard for train control and command systems. The development process was started with the technical foundations for communication (GSM-R) and signalling (ETCS). Both are well established and in advanced public implementation worldwide . Now it begins to start attention for the 3rd part of ETML i.e. for fleet management or passenger information. In

SECTION 20

#1732852484053

1958-436: Is evolving, making use of the latest techniques and components to offer more compact systems and simpler architectures. For instance, with the advent of modern electronics it has been possible to build in redundancy so that single failures do not adversely impact operational availability. Moreover, these systems offer complete flexibility in terms of operational schedules or timetables, enabling urban rail operators to respond to

2047-578: Is generally incompatible with ERTMS / ETCS (as in the case of the Bothnia Line which is the first railway line in Sweden to exclusively use ERTMS/ETCS), and with the aim of Trafikverket to eventually replace ATC-2 with ERTMS/ETCS over the next few decades, a Special Transmission Module (STM) has been developed to automatically switch between ATC-2 and ERTMS/ETCS. In 1906, the Great Western Railway in

2136-658: Is however not used on the Copenhagen S-train commuter network, where another, incompatible safety system called HKT ( da:Hastighedskontrol og togstop ) had been in use from 1975–2022, as well as on the Hornbæk Line , which uses a much more simplified ATP system introduced in 2000. All aforementioned systems are gradually being replaced by the modern and worldwide CBTC signalling standard as of 2024. Bane NOR —the Norwegian government's agency for railway infrastructure—uses

2225-468: Is mixed with NTC of ASFA and LZB . Operational principle of ETCS in mixed operation: NTC and ETCS Level 2 The principle of mixed level signalling is based on simple principles using bi-directional data exchange between the Radio Block Centre (RBC) and the interlocking systems. The operator sets a route and does not need to know if the route will be used for a Level NTC (former LSTM) only or

2314-558: Is possible to run a line with both conventional and ETCS trains and to use the advantages of ETCS technology for the trains so equipped (e.g. higher speed or more trains on the line) but with the benefit that it is not necessary to equip the whole train fleet with ETCS simultaneously. Examples of ETCS in mixed operation include HSL 3 in Belgium where ETCS is mixed with national ATP system TBL or High-Speed Line Cordoba-Malaga in Spain where ETCS

2403-412: Is sortable, and is initially sorted by year. Click on the [REDACTED] icon on the right side of the column header to change sort key and sort order. 2021 (Tuen Ma Line and former West Rail Line) Brownfield (other sections) Greenfield (other sections) Line M4: UTO Line 5, Kelana Jaya Line Line 12, Putrajaya Line Automatic train control Automatic train control ( ATC )

2492-456: Is the location to which the train is permitted to proceed according to a MA. When transmitting a MA, it is the end of the last section given in the MA. The RBC sends a Movement Authority (MA) to the train if a Level 2 train is allocated to the route. Otherwise the signal shows the optical proceed aspect and the related NTC code is sent to the track. As soon as a Level 2 train reports itself in rear of

2581-418: Is the permission for a train to move to a specific location within the constraints of the infrastructure and with supervision of speed. End of Authority is the location to which the train is permitted to proceed and where target speed is equal to zero. End of Movement is the location to which the train is permitted to proceed according to an MA. When transmitting an MA, it is the end of the last section given in

2670-705: Is the system of standards for management and interoperation of signalling for railways by the European Union (EU). It is conducted by the European Union Agency for Railways (ERA) and is the organisational umbrella for the separately managed parts of The main target of ERTMS is to promote the interoperability of trains in the EU. It aims to greatly enhance safety, increase efficiency of train transports and enhance cross-border interoperability of rail transport in Europe . This

2759-402: Is the use of leaky feeder cable that, while having higher initial costs (material + installation) achieves a more reliable radio link. With the emerging services over open ISM radio bands (i.e. 2.4 GHz and 5.8 GHz) and the potential disruption over critical CBTC services, there is an increasing pressure in the international community (ref. report 676 of UITP organization, Reservation of

Communications-based train control - Misplaced Pages Continue

2848-489: Is varying according to the continuous updates of the train location and speed, maintaining the safety requirements. This results in a reduced headway between consecutive trains and an increased transport capacity . Modern CBTC systems allow different levels of automation or grades of automation (GoA), as defined and classified in the IEC 62290–1. In fact, CBTC is not a synonym for " driverless " or "automated trains" although it

2937-584: The BMT Canarsie Line in New York City was outfitted with a backup automatic block signaling system capable of supporting 12 trains per hour (tph), compared with the 26 tph of the CBTC system. Although this is a rather common architecture for resignalling projects, it can negate some of the cost savings of CBTC if applied to new lines. This is still a key point in the CBTC development (and is still being discussed), since some providers and operators argue that

3026-632: The British Rail Automatic Warning System (AWS). Starting in 2017, the Toronto Transit Commission began the implementation of ATC on to Line 1 Yonge–University , at a cost of $ 562.3   million. Awarding the contract to Alstom in 2009, the TTC will be able to reduce the headway between trains on Line 1 during rush hours, and allow an increase in the number of trains operating on Line 1. Work would however not begin until

3115-470: The IEEE 1474 standard. CBTC is a signalling standard defined by the IEEE 1474 standard. The original version was introduced in 1999 and updated in 2004. The aim was to create consistency and standardisation between digital railway signalling systems that allow for an increase in train capacity through what the standard defines as high-resolution train location determination. The standard therefore does not require

3204-472: The Long Island Rail Road require the use of speed control on freight trains that run on all or part of their systems. While cab signalling and speed control technology has existed since the 1920s, adoption of ATC only became an issue after a number of serious accidents several decades later. The Long Island Rail Road implemented its Automatic Speed Control system within its cab signalled territory in

3293-755: The Senseki Line in 2011, followed by the Saikyō Line in 2017, and the Koumi Line in 2020. It is considered to be Japan's equivalent to ETCS Level 3 . Several subway lines in South Korea use ATC, in some cases enhanced with ATO. All lines use ATC. All lines are enhanced with ATO. Other than on Lines 1 and 2 (MELCO cars only), all lines use ATC. Line 2 (VVVF cars), Line 5 cars, Line 6 cars, Line 7 cars, and Line 8 cars have their ATC systems enhanced with ATO. Denmark's system of ATC (officially designated ZUB 123 )

3382-682: The Singapore North East Line . CBTC has its origins in the loop-based systems developed by Alcatel SEL (now Thales ) for the Bombardier Automated Rapid Transit (ART) systems in Canada during the mid-1980s. These systems, which were also referred to as transmission-based train control (TBTC), made use of inductive loop transmission techniques for track to train communication, introducing an alternative to track circuit based communication. This technology, operating in

3471-416: The signalling system perspective, the first figure shows the total occupancy of the leading train by including the whole blocks which the train is located on. This is due to the fact that it is impossible for the system to know exactly where the train actually is within these blocks . Therefore, the fixed block system only allows the following train to move up to the last unoccupied block 's border. In

3560-619: The Åsta accident occurred in 2000, the implementation of DATC on the Røros Line was accelerated, and it became operational in 2001. In Sweden the development of ATC started in the 1960s (ATC-1), and was formally introduced in the early-1980s together with high-speed trains (ATC-2/Ansaldo L10000). As of 2008, 9,831 km out of the 11,904 km of track maintained by Swedish Transport Administration —the Swedish agency responsible for railway infrastructure—had ATC-2 installed. However, since ATC-2

3649-569: The Øresundståg service and some X 2000 trains) have both the Danish and the Swedish systems, while others (e.g. ten of the ICE-TD trains) are fitted with both the Danish and the German systems. The ZUB 123 system is now considered by Banedanmark , the Danish railway infrastructure company, to be obsolete and the entire Danish rail network is expected to be converted to ETCS Level 2 by 2030. The ZUB 123 system

Communications-based train control - Misplaced Pages Continue

3738-802: The 1950s after a pair of deadly accidents caused by ignored signals. After the Newark Bay Lift Bridge Disaster the state of New Jersey legislated use of speed control on all major passenger train operators within the State. While speed control is used on many passenger lines in the United States, in most cases it has been adopted voluntarily by the railroads that own the lines. Only three freight railroads, Union Pacific , Florida East Coast and CSX Transportation , have adopted any form of ATC on their own networks. The systems on both FEC and CSX work in conjunction with pulse code cab signals , which in

3827-542: The 30–60  kHz frequency range to communicate trains and wayside equipment, was widely adopted by the metro operators in spite of some electromagnetic compatibility (EMC) issues, as well as other installation and maintenance concerns (see SelTrac for further information regarding transmission-based train-control). As with new application of any technology, some problems arose at the beginning mainly due to compatibility and interoperability aspects. However, there have been relevant improvements since then, and currently

3916-472: The ATC applies the brakes automatically when the train speed exceeds the speed limit, it cannot control the motor power or train stop position when pulling into stations. However, the automatic train operation (ATO) system can automatically control departure from stations, the speed between stations, and the stop position in stations. It has been installed in some subways. However, ATC has three disadvantages. First,

4005-517: The Automatic Train Control (ATC) system was developed for high-speed trains like the Shinkansen , which travel so fast that the driver has almost no time to acknowledge trackside signals. Although the ATC system sends AF signals carrying information about the speed limit for the specific track section along the track circuit . When these signals are received on board, the train's current speed

4094-478: The ERTMS-route. Depending on the implementation, NTC systems along the route may or may not be active. Movement Authority (MA) is the permission for a train to move to a specific location within the constraints of the infrastructure and with supervision of speed. End of movement Authority (EoA) is the location to which the train is permitted to proceed and where target speed is equal to zero. End of movement Authority

4183-447: The ETCS and ATC balise frequencies are too close so that older trains would get faults when passing Eurobalises . Mixed operation is a strategy where the wayside signalling is equipped with both ETCS and a conventional Class B system. Often the conventional system is the legacy system used during the signalling upgrade program. The main purposes of introducing a mixed operation (mixed signalling system) are: With mixed operation it

4272-462: The MA. It is important to mention that the occupancy calculated in these systems must include a safety margin for location uncertainty (in yellow in the figure) added to the length of the train. Both of them form what is usually called 'Footprint'. This safety margin depends on the accuracy of the odometry system in the train. CBTC systems based on moving block allows the reduction of the safety distance between two consecutive trains. This distance

4361-550: The Sub-Surface network in London Underground ). Despite the difficulty, the table below tries to summarize and reference the main radio-based CBTC systems deployed around the world as well as those ongoing projects being developed. Besides, the table distinguishes between the implementations performed over existing and operative systems ( brownfield ) and those undertaken on completely new lines ( Greenfield ). This list

4450-574: The Swedish system of ATC. Trains can therefore generally cross the border without being specially modified. However, unlike in Sweden, the ATC system used in Norway differentiates between partial ATC ( delvis ATC , DATC), which ensures that a train stops whenever a red signal is passed, and full ATC (FATC), which, in addition to preventing overshooting red signals, also ensures that a train does not exceed its maximum allowed speed limit. A railway line in Norway can have either DATC or FATC installed, but not both at

4539-672: The UIC ERTMS World Conference in Stockholm, Sweden, the executive director of the Community of European Railway and Infrastructure Companies (CER) called for an accelerated implementation of ERTMS in Europe. After definition of ETCS Baseline 3 in about 2010 and starting of implementation in multiple countries with Baseline 3 Release 2 in summer 2016, it is again possible to direct attention to operational management requirements of payloads . Logistics companies like DB Cargo have

SECTION 50

#1732852484053

4628-444: The UK developed a system known as "automatic train control". In modern terminology, GWR ATC is classified as an automatic warning system (AWS). This was an intermittent train protection system that relied on an electrically energised (or unenergised) rail between, and higher than, the running rails. This rail sloped at each end and was known as an ATC ramp and would make contact with a shoe on

4717-407: The United States are almost always integrated with existing continuous cab signalling systems. The ATC comes from electronics in the locomotive that implement some form of speed control based on the inputs of the cab signalling system. If the train speed exceeds the maximum speed allowed for that portion of track, an overspeed alarm sounds in the cab. If the engineer fails to reduce speed and/or make

4806-463: The braking pattern, while ensuring ride comfort. There is also an emergency braking pattern outside the normal braking pattern and the ATC system applies the emergency brakes if the train speed exceeds this emergency braking pattern. The digital ATC system has a number of advantages: To date, the following digital ATC systems are used: ATACS is a moving block ATC system similar to CBTC , developed by RTRI and first implemented by JR East on

4895-524: The case of CSX was inherited from the Richmond, Fredericksburg and Potomac railroad on its single main line. Union Pacific's was inherited on portions of the Chicago and Northwestern east–west main line and works in conjunction with an early two aspect cab signaling system designed for use with ATC. On CSX and FEC more restrictive cab signal changes require the engineer to initiate a minimum brake application or face

4984-643: The case of upgrading existing lines the design, installation, test and commissioning stages are much more critical. This is mainly due to the challenge of deploying the overlying system without disrupting the revenue service. The evolution of the technology and the experience gained in operation over the last 30 years means that modern CBTC systems are more reliable and less prone to failure than older train control systems. CBTC systems normally have less wayside equipment and their diagnostic and monitoring tools have been improved, which makes them easier to implement and, more importantly, easier to maintain. CBTC technology

5073-413: The communications medium. In this case, an interruption can result in a service brake or emergency brake application as real time situational awareness is a critical safety requirement for CBTC and if these interruptions are frequent enough it could seriously impact service. This is the reason why, historically, CBTC systems first implemented radio communication systems in 2003, when the required technology

5162-542: The delivery of brand new trains with ATC compatibility and the retirement of older rolling stock that was not compatible with the new system. ATC was introduced in phases, beginning with a test on 4 November 2017 during regular service between Dupont and Yorkdale stations. It was first introduced in a permanent manner with the opening of the Toronto–York Spadina subway extension on 17 December 2017, between Vaughan and Sheppard West stations. Implementation of

5251-450: The design (e.g. guaranteed emergency brake rate vs. nominal brake rate). For instance, CBTC introduction in Philly's Center City trolley tunnel resulted initially in a marked increase in travel time and corresponding decrease in capacity when compared with the unprotected manual driving. This was the offset to finally eradicate vehicle collisions which on-sight driving cannot avoid and showcases

5340-476: The driver failed to acknowledge this warning within a preset time, the brakes of the train would be applied. In testing, the GWR demonstrated the effectiveness of this system by sending an express train at full speed past a distant signal at caution. The train was brought safely to a stand before reaching the home signal. If the signal associated with the ramp was clear, the ramp was energised. The energized ramp would lift

5429-494: The driver retained full command of braking. The term is especially common in Japan , where ATC is used on all Shinkansen (bullet train) lines, and on some conventional rail and subway lines, as a replacement for ATS. The accident report for the 2006 Qalyoub accident mentions an ATC system. In 2017, Huawei was contracted to install GSM-R partly to provide communication services to automatic train protection systems. In Japan,

SECTION 60

#1732852484053

5518-488: The headway cannot be increased due to the idle running time between releasing the brakes at one speed limit and applying the brakes at the next slower speed limit. Second, the brakes are applied when the train achieves maximum speed, meaning reduced ride comfort. Third, if the operator wants to run faster trains on the line, all the related relevant wayside and on-board equipment must be changed first. The following analogue systems have been used: The digital ATC system uses

5607-497: The initial cab signal drop. Failure to apply the brakes for these speed reductions will result in a penalty application. All three freight ATC systems provide the engineer with a degree of latitude in applying brakes in a safe and proper manner, since improper braking can result in a derailment or a runaway. None of the systems are in effect in difficult or mountainous terrain. European Railway Traffic Management System The European Rail Traffic Management System ( ERTMS )

5696-523: The introduction of ETCS Level 1 (such as in Spain) proved to be expensive and nearly all implementations are delayed. The defined standards were comprehensive by political nature, but not exact in technical means. National rail authorities often had certain features or constraints in their existing system they did not want to lose, and since every authority was still required to approve the systems, dialects of ERTMS emerged. Some active players were willing to overcome

5785-521: The introduction of ETCS the infrastructure manager has to decide whether a line will be equipped only with ETCS or if there is a demand for a mixed signalling system with support for National Train Control (NTC). Currently, both 'clean' and mixed systems are being deployed in Europe and around the world. Many new ETCS lines in Europe are being created and then it may often be preferred to implement ETCS Level 1 or Level 2 only. With this implementation strategy

5874-712: The member states of EU voted for publication of this specifications as decision of the European Commission to get a preliminary security in law and planning. This was to give the foundation for testing applications in six member railways of the ERTMS Users Group . In 2002 the Union of Signalling Industry (UNISIG) published the SUBSET-026 defining the current implementation of ETCS signalling equipment together with GSM–R – this Class 1 SRS 2.2.2 (now called ETCS Baseline 2 )

5963-1040: The mid-1980s, the International Union of Railways (UIC) and the European Rail Research Institute (ERRI) began the search for a common European operation management for railways, titled ERTMS. Today the development of ERTMS is steered by the ERA and driven by the Association of the European Rail Industry (UNIFE, Union des Industries Ferroviaires Européennes). Until this effort began, there were (for historical reasons in each national railway system) in Europe: all influencing train communication in parts. To illustrate this, long running trains like Eurostar or Thalys must have 6 to 8 different train protection systems. Technical targets of ERTMS are: In 1995

6052-409: The modern CBTC systems the trains continuously calculate and communicate their status via radio to the wayside equipment distributed along the line. This status includes, among other parameters, the exact position, speed, travel direction and braking distance . This information allows calculation of the area potentially occupied by the train on the track. It also enables the wayside equipment to define

6141-404: The need to develop functional capabilities in the target scope of ETML, which should be welcome for standardisation. The deployment of the European Rail Traffic Management System means the installation of ETCS components on the lineside of the railways and the train borne equipment. Both parts are connected by GSM-R as the communication part. Various railway roll out strategies can be used. With

6230-435: The next train ahead is computed. The on-board memory also saves data on track gradients, and speed limits over curves and points. All this data forms the basis for ATC decisions when controlling the service brakes and stopping the train. In a digital ATC system, the running pattern creates determines the braking curve to stop the train before it enters the next track section ahead occupied by another train. An alarm sounds when

6319-599: The older automatic train stop (ATS) technology. ATC can also be used with automatic train operation (ATO) and is usually considered to be the safety-critical part of a railway system. There have been numerous different safety systems referred to as "automatic train control" over time. The first experimental apparatus was installed on the Henley branch line in January 1906 by the Great Western Railway , although it would now be referred to as an automatic warning system (AWS) because

6408-418: The points on the line that must never be passed by the other trains on the same track. These points are communicated to make the trains automatically and continuously adjust their speed while maintaining the safety and comfort ( jerk ) requirements. So, the trains continuously receive information regarding the distance to the preceding train and are then able to adjust their safety distance accordingly. From

6497-545: The protected section for each train is a "block" that moves with and trails behind it, and provides continuous communication of the train's exact position via radio, inductive loop, etc. As a result, Bombardier opened the world's first radio-based CBTC system at San Francisco airport 's automated people mover (APM) in February 2003. A few months later, in June 2003, Alstom introduced the railway application of its radio technology on

6586-484: The reliability of the radio-based communication systems has grown significantly. Moreover, it is important to highlight that not all the systems using radio communication technology are considered to be CBTC systems. So, for clarity and to keep in line with the state-of-the-art solutions for operator's requirements, this article only covers the latest moving block principle based (either true moving block or virtual block , so not dependent on track-based detection of

6675-512: The same time. ATC was first trialled in Norway in 1979, after the Tretten train disaster , caused by a signal passed at danger (SPAD), occurred four years earlier. DATC was first implemented on the section Oslo S - Dombås - Trondheim - Grong between 1983 and 1994, and FATC was first implemented on the Ofoten Line in 1993. The high-speed Gardermoen Line has had FATC since its opening in 1998. After

6764-416: The shoe on the passing locomotive and cause a bell to sound on the footplate. If the system were to fail then the shoe would remain unenergised, the caution state; it therefore failed safe , a fundamental requirement of all safety equipment. The system had been implemented on all GWR main lines, including Paddington to Reading, by 1908. The system remained in use until the 1970s, when it was superseded by

6853-586: The situation with a new Baseline definition, not suited for immediate action. This situation shifted the focus more onto the technical parts of ETCS and GSM-R as universal technical foundations of ERTMS. To master this situation, Karel Vinck was appointed in July 2005 as EU coordinator. In 2005 a Memorandum of Understanding on ERTMS was published by members of the European Commission, national railways and supplying industries in Brussels . According to this declaration ETCS

6942-477: The specific traffic demand more swiftly and efficiently and to solve traffic congestion problems. In fact, automatic operation systems have the potential to significantly reduce the headway and improve the traffic capacity compared to manual driving systems. Finally, it is important to mention that the CBTC systems have proven to be more energy efficient than traditional manually driven systems. The use of new functionalities, such as automatic driving strategies or

7031-462: The system on to the remainder of the line was carried out during weekend closures and night time work when the subway would close. There were delays on the project, with deadlines for the complete conversion of Line 1 pushed back multiple times until 2022. ATC conversion was completed to Finch station on 24 September 2022. Converting all of Line 1 to ATC required the installation of 2,000 beacons, 256 signals, and more than one million feet of cable. ATC

7120-407: The track circuits to detect the presence of a train in the section and then transmits digital data from wayside equipment to the train on the track circuit numbers, the number of clear sections (track circuits) to the next train ahead, and the platform that the train will arrive at. The received data is compared with data about track circuit numbers saved in the train on-board memory and the distance to

7209-433: The train approaches the braking pattern and the brakes are applied when the braking pattern is exceeded. The brakes are applied lightly first to ensure better ride comfort, and then more strongly until the optimum deceleration is attained. The brakes are applied more lightly when the train speed drops to a set speed below the speed limit. Regulating the braking force in this way permits the train to decelerate in accordance with

7298-498: The trains) CBTC solutions that make use of the radio communications . CBTC systems are modern railway signaling systems that can mainly be used in urban railway lines (either light or heavy ) and APMs , although it could also be deployed on commuter lines . For main lines , a similar system might be the European Railway Traffic Management System ERTMS Level 3 (not yet fully defined ). In

7387-400: The underside of the passing locomotive. The ramps were provided at distant signals . A development of the design, intended for use at stop signals, was never implemented. If the signal associated with the ramp was at caution, the ramp would not be energised. The ramp would lift the shoe on the passing locomotive and start a timer sequence at the same time sounding a horn on the footplate. If

7476-408: The use of moving block railway signalling, but in practice this is the most common arrangement. Traditional signalling systems detect trains in discrete sections of the track called ' blocks ', each protected by signals that prevent a train entering an occupied block. Since every block is a fixed section of track, these systems are referred to as fixed block systems. In a moving block CBTC system

7565-401: The usual conflicts between operation and safety. The typical architecture of a modern CBTC system comprises the following main subsystems: Thus, although a CBTC architecture is always depending on the supplier and its technical approach, the following logical components may be found generally in a typical CBTC architecture: CBTC technology has been (and is being) successfully implemented for

7654-718: The wayside signalling cost is kept to a minimum, but the vehicle fleet that operates on these lines will need to all be equipped with ETCS on board to allow operation. This is more suitable for new high-speed passenger lines, where new vehicles will be bought, less suitable if long-distance freight trains shall use it. Examples of 'clean' ETCS operation include HSL-Zuid in the Netherlands, TP Ferro international stretch (Sección Internacional / Section Internationale ) Figueres [ES] – Perpignan [FR], Erfurt–Halle/Leipzig in Germany , among others. Also all ETCS railways in Sweden and Norway, since

7743-487: Was accepted by the European Commission in decision 2002/731/EEC as mandatory for high-speed rail and in decision 2004/50/EEC as mandatory for conventional rail. In 2004 further development stalled. While some countries ( Austria , Spain , Switzerland ) switched to ETCS with some benefit, German and French railway operators had already introduced proven and modern types of domestic train protection systems for high speed traffic, so they would gain no benefit. Furthermore,

7832-413: Was mature enough for critical applications. In systems with poor line of sight or spectrum/bandwidth limitations a larger than anticipated number of transponders may be required to enhance the service. This is usually more of an issue with applying CBTC to existing transit systems in tunnels that were not designed from the outset to support it. An alternate method to improve system availability in tunnels

7921-615: Was to be introduced in 10 to 12 years on a named part of the Trans-European Networks . Following this a conference was held in April 2006 in Budapest for the introduction of ERTMS, attended by 700 people. In July 2009, the European Commission announced that ETCS is now mandatory for all EU funded projects which include new or upgraded signalling and GSM-R is required when radio communications are upgraded. In April 2012 at