Misplaced Pages

Ilısu Dam

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

The Ilısu Dam ( Turkish pronunciation: [ɯɫɯˈsu] ) is a concrete-face rock-fill dam on the Tigris near the village of Ilısu and along the border of Mardin and Şırnak Provinces in Turkey . It is one of the 22 dams of the Southeastern Anatolia Project and its purpose is hydroelectric power production, flood control and water storage. When operational, the dam will support a 1,200 MW power station and will form a 10.4 billion m reservoir. Construction of the dam began in 2006 and was originally expected to be completed by 2016. As part of the project, the much smaller Cizre Dam is to be constructed downstream for irrigation and power. The dam has drawn international controversy, because it will flood portions of ancient Hasankeyf and necessitate the relocation of people living in the region. Because of this, the dam lost international funding in 2008. Most historical structures in Hasankeyf were moved to the new Hasankeyf prior to the filling of the dam. The dam began to fill its reservoir in late July 2019. Due to rainfall, the dam has achieved water levels up to 100m above the river bed and stored 5 billion cubic meters of water. The water level had reached an elevation of 498.2m on 1 April 2020.

#370629

43-409: DSI has started testing 2 turbines for energy production after completing the spillway testing. The dam reservoir has attained a water volume of 7.6 billion cubic meters. Water storage crest level was 513m on 19 April 2020. It would need 12m rise to achieve the maximum storage level. The first of six generators was commissioned on 19 May 2020, while its power plant is scheduled to reach full capacity by

86-402: A fuse plug . If present, the fuse plug is designed to wash out in case of a large flood, greater than the discharge capacity of the spillway gates. Although many months may be needed for construction crews to restore the fuse plug and channel after such an operation, the total damage and cost to repair is less than if the main water-retaining structures had been overtopped. The fuse plug concept

129-443: A baffle of concrete blocks but usually have a "flip lip" and/or dissipator basin, which creates a hydraulic jump , protecting the toe of the dam from erosion. Stepped channels and spillways have been used for over 3,000 years. Despite being superseded by more modern engineering techniques such as hydraulic jumps in the mid twentieth century, since around 1985 interest in stepped spillways and chutes has been renewed, partly due to

172-463: A few dams lack overflow spillways and rely entirely on bottom outlets. The two main types of spillways are controlled and uncontrolled. A controlled spillway has mechanical structures or gates to regulate the rate of flow. This design allows nearly the full height of the dam to be used for water storage year-round, and flood waters can be released as required by opening one or more gates. An uncontrolled spillway, in contrast, does not have gates; when

215-456: A figure of 71,186. The official Turkish government line was expressed by then-Prime Minister Recep Tayyip Erdoğan at the ground-breaking ceremony in 2006: "The step that we are taking today demonstrates that the south-east is no longer neglected. This dam will bring big gains to the local people." The government says the project will generate 10,000 jobs, spur agricultural production through irrigation and boost tourism, although others argue that

258-522: A halt in farming rice, corn, sesame, sunflower seeds and cotton; and a decrease in the area planted for wheat and barley by half for the 2018–19 season. Spillway A spillway is a structure used to provide the controlled release of water downstream from a dam or levee , typically into the riverbed of the dammed river itself. In the United Kingdom, they may be known as overflow channels . Spillways ensure that water does not damage parts of

301-654: A normal elevation of 525 m (1,722 ft) above sea level, the reservoir surface area will cover 313 km (121 sq mi). Beginning in 1954 the Turkish government surveyed 53 kilometres (33 miles) of the Tigris river downstream of Diyarbakır with the aim of identifying suitable locations for a hydroelectric power plant at an elevation below 550 metres (1,800 ft). Turkey's Electric Power Resources Survey and Development Administration (EIE) included 10 potential sites in its 1971 Tigris River Pre-Investigation Report. By 1975,

344-565: A plunge pool, or two ski jumps can direct their water discharges to collide with one another. Third, a stilling basin at the terminus of a spillway serves to further dissipate energy and prevent erosion. They are usually filled with a relatively shallow depth of water and sometimes lined with concrete. A number of velocity-reducing components can be incorporated into their design to include chute blocks, baffle blocks, wing walls, surface boils, or end sills. Spillway gates may operate suddenly without warning, under remote control. Trespassers within

387-607: A spillway gate can result in the stranding of fish, and this is usually avoided. Silvan Dam Silvan Dam is an embankment concrete-face rock-fill currently under construction on the Batman River in the district of Silvan , Diyarbakır Province in southeastern Turkey . It is part of the Southeastern Anatolia Project and located upstream of the Batman Dam . Construction began on 26 July 2011. The purpose of

430-471: A spillway only during flood periods, when the reservoir has reached its capacity and water continues entering faster than it can be released. In contrast, an intake tower is a structure used to control water release on a routine basis for purposes such as water supply and hydroelectricity generation. A spillway is located at the top of the reservoir pool. Dams may also have bottom outlets with valves or gates which may be operated to release flood flow, and

473-460: Is designed like an inverted bell , where water can enter around the entire perimeter. These uncontrolled spillways are also called morning glory (after the flower ), or glory hole spillways. In areas where the surface of the reservoir may freeze, this type of spillway is normally fitted with ice-breaking arrangements to prevent the spillway from becoming ice-bound. Some bell-mouth spillways are gate-controlled. The highest morning glory spillway in

SECTION 10

#1732851394371

516-624: Is less than 12m from the maximum conservation level of 525m, according to CNN Türk citing the State Hydraulic Works (DSI) by an AA correspondent. Completion of the Ilısu Dam caused the flooding of the majority of the ancient city of Hasankeyf , whose history stretches back over 10,000 years. About 199 settlements (villages and hamlets) will be fully or partially affected by flooding as well. This figure excludes vacant settlements, which will also be inundated. Three decades of conflict between

559-443: Is set by dam safety guidelines, based on the size of the structure and the potential loss of human life or property downstream. The United States Army Corps of Engineers bases their requirements on the probable maximum flood (PMF) and the probable maximum precipitation (PMP). The PMP is the largest precipitation thought to be physically possible in the upstream watershed. Dams of lower hazard may be allowed to have an IDF less than

602-604: Is used where building a spillway with the required capacity would be costly. A chute spillway is a common and basic design that transfers excess water from behind the dam down a smooth decline into the river below. These are usually designed following an ogee curve . Most often, they are lined on the bottom and sides with concrete to protect the dam and topography. They may have a controlling device and some are thinner and multiply-lined if space and funding are tight. In addition, they are not always intended to dissipate energy like stepped spillways. Chute spillways can be ingrained with

645-528: The 2006 ground-breaking ceremony, German, Swiss and Austrian export credit agencies had agreed to fund $ 610 million of the project. In December 2008, the European firms suspended funds for the dam and gave Turkey a 180-day period to comply with over 150 international standards. In June 2009, after failing to meet the standards, the European firms officially cut the funding for the Ilısu Dam Project. Shortly after

688-651: The EIE had completed a technical and economic evaluation of the sites. Ilısu was selected as the preferred site for geological reasons. A feasibility study and final design by international consultants (1980–82) resulted in a recommendation to construct both the Ilısu Dam and the Cizre Dam downstream. There was little movement on the project for more than 15 years until the dam was added to the State Hydraulic Works' formal construction program in 1997 or 1998. On 5 August 2006,

731-460: The PMF. As water passes over a spillway and down the chute, potential energy converts into increasing kinetic energy . Failure to dissipate the water's energy can lead to scouring and erosion at the dam's toe (base). This can cause spillway damage and undermine the dam's stability. To put this energy in perspective, the spillways at Tarbela Dam could, at full capacity, produce 40,000 MW; about 10 times

774-538: The Turkish government and the PKK has resulted in the depopulation of many hamlets in the area, and so now their original inhabitants will never be able to return home either, in addition to the others who still live in the region. In 2006, the Turkish government estimated that 61,620 people would be "physically or economically displaced". Using 1990 census data, it had previously estimated that 55,127 people would be affected; updating these calculations using 2000 survey data produced

817-519: The announcement of the funding loss, Turkey's Environment Minister Veysel Eroğlu said, "Let me tell you this, these power plants will be built. No one can stop it. This is the decision of the state and the government." Turkey's Prime Minister Recep Tayyip Erdoğan is also committed to the Ilısu Dam Project as well and claims Turkey will use internal or other international funding. Turkey stated that construction would start again in July 2009. In February 2010, it

860-407: The capacity of its power plant. The energy can be dissipated by addressing one or more parts of a spillway's design. First, on the spillway surface itself by a series of steps along the spillway (see stepped spillway ). Second, at the base of a spillway, a flip bucket can create a hydraulic jump and deflect water upwards. A ski jump can direct water horizontally and eventually down into

903-454: The dam is hydroelectric power production and irrigation. It is designed to irrigate an area of 245,000 ha (610,000 acres). The power station will have an installed capacity of 160 MW. In 2014, the dam, as well as other in southeast Turkey such as the Ilisu Dam , became a prime target of Kurdistan Workers' Party (PKK) militants after peace talks collapsed with the government. Attacks on

SECTION 20

#1732851394371

946-558: The dam was completed. On 1 June 2018, the reservoir was to begin impoundment but was delayed until November then 2019 following another detail due to water shortages in Iraq. Impoundment began in late July 2019. As of November 2019, the hydroelectric power generation would start in February 2020. Due to rainfalls dam has achieved the water elevation level of 498.2m as of 1 April 2020. Ilisu Dam has attained water level of 513m on 19 April 2020, and it

989-573: The dam, supporting structures and workers are part of the PKK's efforts to stop construction. These attacks delayed construction by 2 years. The construction of the Silvan Tunnel which brings the water from the dam to the surrounding plains started in June 2019. The dam body was completed in January 2021 and some sources say the entire project was completed in the end of 2022. As of 2024 other sources say it

1032-414: The difference in height between the intake and the outlet to create the pressure difference required to remove excess water. Siphons require priming to remove air in the bend for them to function, and most siphon spillways are designed to use water to automatically prime the siphon. One such design is the volute siphon, which employs volutes or fins on a funnel to form water into a vortex that draws air out of

1075-618: The end of 2020. Three hydro-turbines have been commissioned since 19 June 2020 and the remaining three are being tested. So far the dam has contributed 51M$ energy towards economy. The Ilısu Dam will be a 135 m (443 ft) high and 1,820 m (5,971 ft) wide rock-fill embankment dam with a structural volume of 43,900,000 m (35,590 acre⋅ft). It will be 15 m (49 ft) wide at its crest and 610 m (2,001 ft) wide at its base. The dam will have an overflow spillway on its right bank which will be controlled by eight radial gates which will pour into four chutes before

1118-510: The end of June in the same year, due to the fact that the Tigris river has its highest levels during spring time. However, water shortages were witnessed in the Mosul dam , where water in the reservoir had more than 3 billion cubic meters compared with its levels of more than 8 billion cubic meters in the same period of the previous year. Moreover, the southern governorates of Iraq had the lowest portions of

1161-562: The first loads of fill were laid in January 2012. Diversion of the Tigris River began during a ceremony on 29 August 2012. As of April 2014, the project is 60% complete while the resettlement of Hasankeyf is 73% complete. All works are expected to be completed in 2015. In 2014, the dam, as well as others in southeast Turkey such as the Silvan Dam , became a prime target of Kurdistan Workers' Party (PKK) militants after peace talks collapsed with

1204-423: The flood is sometimes expressed as a return period . A 100-year recurrence interval is the flood magnitude expected to be exceeded on the average of once in 100 years. This parameter may be expressed as an exceedance frequency with a 1% chance of being exceeded in any given year. The volume of water expected during the design flood is obtained by hydrologic calculations of the upstream watershed. The return period

1247-526: The foundation stone for the dam was laid and initial construction began. To avoid inflation and other economic repercussions, the Turkish Government has often sought outside assistance to fund the Ilısu Dam Project. However, pressure from environmental and human rights groups have often halted this process. In 2000, the British Government declined $ 236 million in funding for the Ilısu Dam. Before

1290-430: The government. Attacks on the dam, supporting structures and workers are part of the PKK's efforts to stop construction. Construction of the dam was suspended temporarily late in the year. On 3 February 2015, a convoy of supplies for the dam was attacked, injuring three. Several days later a worker was killed in his home by suspected PKK militants. The construction reached 96% in June 2017. In February 2018, construction on

1333-411: The reservoir is controlled by the mechanical gates. In this case, the dam is not designed to function with water flowing over the top if it, either due to the materials used for its construction or conditions directly downstream. If inflow to the reservoir exceeds the gate's capacity, an artificial channel called an auxiliary or emergency spillway will convey water. Often, that is intentionally blocked by

Ilısu Dam - Misplaced Pages Continue

1376-456: The river downstream. One parameter of spillway design is the largest flood it is designed to handle. The structures must safely withstand the appropriate spillway design flood (SDF), sometimes called the inflow design flood (IDF). The magnitude of the SDF may be set by dam safety guidelines, based on the size of the structure and the potential loss of human life or property downstream. The magnitude of

1419-604: The river in years, in which the total Tigris water share in Iraq fell from 21 billion cubic metres to only 9.7 billion cubic metres instead. Such impacts which might lead to the drainage of the Mesopotamian Marshes and destruction of its ecology system, were part of the reasons to the emergence of a new wave of Iraqi protests , along with several other issues, especially in Basra Governorate . In addition, water shortages, lack of rainfall and depleted soils led nearly to

1462-414: The spillway are at high risk of drowning. Spillways are usually fenced and equipped with locked gates to prevent casual trespassing within the structure. Warning signs, sirens, and other measures may be in place to warn users of the downstream area of sudden release of water. Operating protocols may require "cracking" a gate to release a small amount of water to warn persons downstream. The sudden closure of

1505-539: The structure not designed to convey water. Spillways can include floodgates and fuse plugs to regulate water flow and reservoir level. Such features enable a spillway to regulate downstream flow—by releasing water in a controlled manner before the reservoir is full, operators can prevent an unacceptably large release later. Other uses of the term "spillway" include bypasses of dams and outlets of channels used during high water, and outlet channels carved through natural dams such as moraines . Water normally flows over

1548-424: The system. The priming happens automatically when the water level rises above the inlets. The ogee crest over-tops a dam, a side channel wraps around the topography of a dam, and a labyrinth uses a zig-zag design to increase the sill length for a thinner design and increased discharge. A drop inlet resembles an intake for a hydroelectric power plant, and transfers water from behind the dam directly through tunnels to

1591-449: The tourism industry will be ruined due to the loss of Hasankeyf and that the local people will be forced to move to cities because the amount of money they were given to buy new homes in the region is insufficient. After the completion of the dam's construction in early spring 2018, the Iraqi government approached the Turkish authorities to postpone filling of the proposed Ilısu reservoir until

1634-474: The use of new construction materials (e.g. roller-compacted concrete , gabions ) and design techniques (e.g. embankment overtopping protection). The steps produce considerable energy dissipation along the chute and reduce the size of the required downstream energy dissipation basin. Research is still active on the topic, with newer developments on embankment dam overflow protection systems, converging spillways and small weir design. A bell-mouth spillway

1677-510: The water reaches a plunge pool. Its power station will be above ground and will contain 6 x 200 MW Francis turbine -generators with an expected annual generation of 3,833 GWh and gross hydraulic head of 122.6 m (402 ft). The dam's reservoir will have a capacity of 10,400,000,000 m (8,431,417 acre⋅ft), of which 7,460,000,000 m (6,050,000 acre⋅ft) will be active (or live, useful) storage and 2,950,000,000 m (2,390,000 acre⋅ft) will be inactive (dead) storage. At

1720-474: The water rises above the lip or crest of the spillway, it begins to be released from the reservoir. The rate of discharge is controlled only by the height of water above the reservoir's spillway. The fraction of storage volume in the reservoir above the spillway crest can only be used for the temporary storage of floodwater; it cannot be used as water supply storage because it sits higher than the dam can retain it. In an intermediate type, normal level regulation of

1763-669: The world is at Hungry Horse Dam in Montana, U.S., and is controlled by a 64-by-12-foot (19.5 by 3.7 m) ring gate. The bell-mouth spillway in Covão dos Conchos reservoir in Portugal is constructed to look like a natural formation. The largest bell-mouth spillway is in Geehi Dam , in New South Wales, Australia, measuring 105 ft (32 m) in diameter at the lake's surface. A siphon uses

Ilısu Dam - Misplaced Pages Continue

1806-424: Was announced that loans had been granted and the project would continue. On 15 July 2010, Andritz Hydro lifted a temporary suspension on supplying parts to the project and announced it would provide the six 200 MW Francis turbines for the power plant. As part of early and ongoing construction, 52 km (32 mi) of roads are subject to raising and repairing work. A 110 m (361 ft) long temporary bridge

1849-455: Was constructed upstream of the dam site which is supported by 30 sections of steel pipe. Additionally, a 250 m (820 ft) permanent steel-girder bridge with concrete supports was constructed just downstream of the dam. Construction of new Ilısu and Koçtepe villages were underway as well as the relocation of major portions of Hasankeyf. Excavations for the main body of the dam began in May 2011 and

#370629