Misplaced Pages

HVDC Cross-Channel

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

The HVDC Cross-Channel ( French : Interconnexion France Angleterre IFA 2000 ) is the 73-kilometre-long (45 mi) high-voltage direct current (HVDC) interconnector that has operated since 1986 under the English Channel between the continental European grid at Bonningues-lès-Calais and the British electricity grid at Sellindge . The cable is also known as IFA , and should not be confused with the new IFA-2 , another interconnect with France that is three times as long but only half as powerful.

#285714

36-580: The current 2,000   MW link is bi-directional and the countries can import or export depending upon market demands, mostly depending upon weather conditions and availability of renewable energy on the British Isles, and French surplus of nuclear generation or demand for electric heating. It was completed in 1986, and replaced the first cross-Channel link which was a 160   MW link completed in 1961 and decommissioned in 1984. A fire in September 2021 caused

72-586: A major fire at the Sellindge converter station led to the shutdown of the link. National Grid initially announced that half of the link capacity would be restored within a fortnight, with full capacity being restored in March 2022. The shutdown came at a time of high prices and supply shortage in the UK electricity market, caused by low wind speeds and high prices for natural gas. On 15 October 2021, National Grid announced that half of

108-673: A merger with the Swiss company Brown, Boveri & Cie (BBC) to form ABB . The merge took effect on 1 January 1988. After this merger, ABB acquired several companies, including the power transmission and distribution operations of the Westinghouse Electric Corporation and the Combustion Engineering Group. This Swedish corporation or company article is a stub . You can help Misplaced Pages by expanding it . This article about an industrial corporation or company

144-485: A ship dragging an anchor cut four of the eight cable components, reducing capacity by 50%. Repairs were completed by the end of February 2017. The equipment occasionally faults, causing capacity to drop: in a bad year, this might happen several times. To maintain grid frequency and power, the National Grid has a variety of frequency response assets, of which market batteries are the first to respond. In September 2021,

180-564: Is a stub . You can help Misplaced Pages by expanding it . Frequency response (electrical grid) Power system operations is a term used in electricity generation to describe the process of decision-making on the timescale from one day ( day-ahead operation ) to minutes prior to the power delivery . The term power system control describes actions taken in response to unplanned disturbances (e.g., changes in demand or equipment failures) in order to provide reliable electric supply of acceptable quality. The corresponding engineering branch

216-499: Is called Power System Operations and Control . Electricity is hard to store, so at any moment the supply (generation) shall be balanced with demand (" grid balancing "). In an electrical grid the task of real-time balancing is performed by a regional-based control center, run by an electric utility in the traditional ( vertically integrated ) electricity market. In the restructured North American power transmission grid , these centers belong to balancing authorities numbered 74 in 2016,

252-416: Is engaged automatically within seconds after the frequency disturbance. Primary control stabilizes the situation, but does not return the conditions to the normal and is applied both to the generation side (where the governor adjusts the power of the prime mover ) and to the load, where: Another term commonly used for the primary control is frequency response (or "beta"). Frequency response also includes

288-428: Is low availability of hydroelectric power. As of 2005, imports of electricity from France have historically accounted for about 5% of electricity available in the UK. Imports through the interconnector have generally been around the highest possible level, given the capacity of the link. In 2006, 97.5% of the energy transfers were made from France to UK, supplying the equivalent of 3   million English homes. Prior to

324-458: Is subject to multiple constraints: In the hours prior to the delivery, a system operator might need to deploy additional supplemental reserves or even commit more generation units, primarily to ensure the reliability of the supply while still trying to minimize the costs. At the same time, operator must ensure that enough reactive power reserves are available to prevent the voltage collapse . The decisions (" economic dispatch ") are based on

360-516: Is too much supply, the devices absorb the excess, and frequency goes above the scheduled rate, conversely, too much demand causes the generator to deliver extra electricity through slowing down, with frequency slightly decreasing, not requiring an intervention from the operator. There are obvious limits to this "immediate control", so a control continuum is built into a typical power grid, spanning reaction intervals from seconds ("primary control") to hours ("time control"). The primary control

396-482: The dispatch curve , where the X-axis constitutes the system power, intervals for the generation units are placed on this axis in the merit order with the interval length corresponding to the maximum power of the unit, Y-axis values represent the marginal cost (per- MWh of electricity, ignoring the startup costs). For cost-based decisions, the units in the merit order are sorted by the increasing marginal cost. The graph on

SECTION 10

#1732851533286

432-490: The inertial response of the generators. This is the parameter that is approximated by the frequency bias coefficient of the area control error (ACE) calculation used for automatic generation control . The secondary control is used to restore the system frequency after a disturbance, with adjustments made by the balancing authority control computer (this is typically referred to as load-frequency control or automatic generation control ) and manual actions taken by

468-400: The nuclear power stations take a very long time to start, while hydroelectric plants require planning of water resources usage way in advance, therefore commitment decisions for these are made weeks or even months before prior to the delivery. For a "traditional" vertically integrated electric utility the main goal of the unit commitment is to minimize both the marginal cost of producing

504-446: The "intermediate" or "cycling" capacity. If the demand goes above 200 MW only occasionally, the unit C will be idle most of the time and will be considered a peaking power plant (a "peaker"). Since a peaker might run for just tens of hours per year, the cost of peaker-produced electricity can be very high in order to recover the capital investment and fixed costs (see the right side of a hypothetical full-scale dispatch curve). Sometimes

540-558: The 2021 fire, the link availability was around 98%, which was among the best rates in the world. The continued size and duration of the flows are open to some doubt, given the growth in demand in continental Europe for clean electricity, and increasing electricity demand within France. Download coordinates as: Download coordinates as: ASEA Allmänna Svenska Elektriska Aktiebolaget ( English translation: General Swedish Electrical Limited Company ; Swedish abbreviation: ASEA )

576-420: The balancing authority staff. Secondary control uses both the spinning and non-spinning reserves, with balancing services deployed within minutes after disturbance (hydropower plants are capable of an even faster reaction). The tertiary control involves reserve deployment and restoration to handle the current and future contingencies. The goal of the time control is to maintain the long-term frequency at

612-412: The calculations by hand, so from the 1920s the calculations were automated, at first in the form of specially-built analog computers , so called network analyzers , replaced by digital computers in the 1960s. Small mismatches between the total demand and total load are typical and initially are taken care of by the kinetic energy of the rotating machinery (mostly synchronous generators ): when there

648-408: The cost incurred are allocated either to participants responsible for the disruption based on preestablished tariffs or in equal shares. In the minutes prior to the delivery, a system operator is using the power-flow study algorithms in order to find the optimal power flow . At this stage the goal is reliability ("security") of the supply. The practical electric networks are too complex to perform

684-440: The cost per hour of operation (ignoring the startup costs, $ 30 * 120 + $ 60 * 30 = $ 5,400 per hour), the incremental cost of the next MWh of electricity ($ 60 in the example, represented by a horizontal line on the graph) is called system lambda (thus another name for the curve, system lambda curve ). In real systems the cost per MWh usually is not constant, and the lines of the dispatch curve are therefore not horizontal (typically

720-542: The entities responsible for operations are also called independent system operators , transmission system operators. The other form of balancing resources of multiple power plants is a power pool . The balancing authorities are overseen by reliability coordinators . Day-ahead operation schedules the generation units that can be called upon to provide the electricity on the next day ( unit commitment ). The dispatchable generation units can produce electricity on demand and thus can be scheduled with accuracy. The production of

756-402: The grid constraints change unpredictably and a need arises to change the previously set unit commitments. This system redispatch change is controlled in real-time by the central operator issuing directives to market participants that submit in advance bids for the increase/decrease in the power levels. Due to the centralized nature of redispatch, there is no delay to negotiate terms of contracts;

SECTION 20

#1732851533286

792-428: The link capacity would be restored within the next few days, that 75% capacity would be available between October 2022 and May 2023, and that they hoped to restore full capacity by October 2023. Since the commissioning of the 2,000   MW DC link in the 1980s, the bulk of power flow through the link has been from France to Britain. However, France imports energy as needed during the winter to meet demand, or when there

828-517: The link consist of 8   cables with lengths of 18.5 km (11.5 miles) in England, and 6.35 km (3.95 miles) in France. In common with the 1961 scheme, there is no provision to permit neutral current to flow through the sea. Although each station includes an earth electrode, this is used only to provide a neutral reference, and only one of the two electrodes is connected at a given time so that there can be no current flow between them. The system

864-423: The link to be removed from service. National Grid announced that half of its capacity would be restored on 20 October 2021, with full capacity being restored by October 2023. The first HVDC Cross-Channel scheme was built by ASEA and went into service in 1961, between converter stations at Lydd in England (next to Dungeness Nuclear Power Station ) and Echinghen , near Boulogne-sur-Mer , in France. This scheme

900-481: The marginal cost of power increases with the dispatch level, although for the combined cycle power plants there are multiple cost curves depending on the mode of operation, so the power-cost relationship is not necessarily monotonic ). If the minimum level of demand in the example will stay above 120 MW, the unit A will constantly run at full power, providing baseload power , unit B will operate at variable power, and unit C will need to be turned on and off, providing

936-404: The right describes an extremely simplified system, with three committed generator units (fully dispatchable, with constant per-MWh cost): At the expected demand is 150 MW (a vertical line on the graph), unit A will be engaged at full 120 MW power, unit B will run at the dispatch level of 30 MW, unit C will be kept in reserve. The area under the dispatch curve to the left of this line represents

972-466: The same manufacturer, the two converter stations of the 2,000   MW scheme were built by different manufacturers (although both have subsequently become part of the same parent company, Alstom ). The Sellindge converter station was built by GEC and the Les Mandarins converter station was built by CGE Alstom. This HVDC-link is 73 km (45 miles) long in route, with 70 km (43 miles) between

1008-521: The specified value within a wide area synchronous grid . Due to the disturbances, the average frequency drifts, and a time error accumulates between the official time and the time measured in the AC cycles. In the US, the average 60 Hz frequency is maintained within each interconnection by a designated entity, time monitor , that periodically changes the frequency target of the grid ( scheduled frequency ) to bring

1044-423: The two ends. The undersea section consists of eight 46 km (29 miles) long 270   kV submarine cables , laid between Folkestone (UK) and Sangatte (France), arranged as two fully independent 1,000   MW Bipoles, each operated at a DC voltage of ±270   kV. Cables are laid in pairs in four trenches so that the magnetic fields generated by the two conductors are largely cancelled. The landside parts of

1080-423: The unit electricity and the (quite significant for fossil fuel generation) start-up costs. In a "restructured" electricity market a market clearing algorithm is utilized, frequently in a form of an auction ; the merit order is sometimes defined not just by the monetary costs, but also by the environmental concerns. Unit commitment is more complex than the shorter-time-frame operations, since unit availability

1116-486: The weather-dependent variable renewable energy for the next day is not certain, its sources are thus non-dispatchable. This variability, coupled with uncertain future power demand and the need to accommodate possible generation and transmission failures requires scheduling of operating reserves that are not expected to produce electricity, but can be dispatched on a very short notice. Some units have unique features that require their commitment much earlier: for example,

HVDC Cross-Channel - Misplaced Pages Continue

1152-513: Was 160   megawatts (MW). The cable was built by ABB . Given that the cable was laid on the surface of the seabed it was prone to being fouled by fishing nets, causing damage. Whilst repairs were undertaken there was considerable down time on the circuit resulting in a loss of trading. Indeed, by 1984 the circuit was disconnected from the Main Transmission System. Because the first installation did not meet increasing requirements, it

1188-501: Was a Swedish industrial company. ASEA was founded in 1883 by Ludvig Fredholm in Västerås as a manufacturer of electrical light and generators. After merging with Wenström's & Granström's Electrical Power Company ( Wenströms & Granströms Elektriska Kraftbolag ) the name was changed to Allmänna Svenska Elektriska Aktiebolaget , literally the "General Swedish Electrical Limited Company", or ASEA for short. In 1987, it announced

1224-448: Was built with solid-state semiconductor thyristor valves from the outset. Initially these were air-cooled and used analogue control systems, and in 2011 and 2012 respectively, the thyristor valves of Bipole 1 and Bipole 2 were replaced by modern water-cooled thyristor valves and digital control systems supplied by Alstom. This system remains the world's largest-capacity submarine cable HVDC system. In November 2016, during Storm Angus ,

1260-410: Was equipped with mercury-arc valves , each having four anodes in parallel. In order to keep the disturbances of the magnetic compasses of passing ships as small as possible, a bipolar cable was used. The cable had a length of 65 km (40 miles) and was operated symmetrically at a voltage of ±100   kV and a maximum current of 800   amperes. The maximum transmission power of this cable

1296-625: Was replaced in 1975–1986 by a new HVDC system with a maximum transmission rating of 2,000   MW between France and the United Kingdom, for which two new converter stations were built in Sellindge , between Ashford and Folkestone in Kent , England and in Bonningues-lès-Calais (Les Mandarins station), near Calais , France. Unlike most HVDC schemes, where the two converter stations are built by

#285714