Conestoga Mall is a shopping mall located at 550 King Street North in Waterloo , Ontario , Canada. Located at King Street's interchange with the Conestoga Parkway , it is the largest shopping centre in Waterloo, and third-largest in Waterloo Region . The mall is owned and operated by Primaris REIT.

#790209

50-660: The consortium named GrandLinq is the successful bidder to build and operate the Ion rapid transit system in Waterloo Region, Ontario . GrandLinq was one of three groups invited to bid on the system in February 2013. GrandLinq's partners include: Plenary Group Canada; Meridiam Infrastructure Waterloo ; Aecon ; Kiewit ; Mass Electric Construction Canada; Keolis ; STV Canada Construction; AECOM ; and CIBC World Markets . In 2012, seven groups of partners indicated an interest in bidding on

100-454: A Flexity Freedom running under its own power at the Ion maintenance facility. The two-hour test was done at the speed of 10 km/h (6.2 mph) and "apparently went quite well", according to Coun. Tom Galloway. In 2018, testing beyond the maintenance facility was scheduled to start. By this date, Waterloo Region had three LRVs on site, which is the minimum number required to do an adequate test of

150-457: A Food Court featuring 14 vendors and a Galaxy Cinema. Anchor tenants include Hudson's Bay , Zehrs , Galaxy Cinemas , Winners , Sport Chek , Old Navy , and Shoppers Drug Mart . The mall, built in 1978, was one of the only buildings on this section of King Street. Since it opened, the mall has been expanded several times, and has contributed to the retail success of this area. Several big box retailers have opened on King Street North around

200-420: A daily ridership of 11,780. In 2009, an Environmental Assessment (EA) began to create a proposal of electrically powered light rail transit through Kitchener and Waterloo, and adapted bus rapid transit from Kitchener to Cambridge. On June 24, 2009, Regional Council voted to approve the project, subject to funding from higher levels of government, which was in turn approved by council on June 15, 2011. This

250-535: A frequency of every 10 minutes from 6   am to 10   pm on weekdays and 15 minutes at other times. The route is properly known as 301 ION Light Rail . The maximum operating speed of Ion light rail vehicles is 50 km/h (31 mph) along city streets and 70 km/h (43 mph) along railway rights of way. However, in areas where there is high pedestrian traffic, the operating speed will be as low as 20–25 km/h (12–16 mph). The 19-kilometre (12 mi) trip from Conestoga Mall to Fairview Park Mall

300-535: A mix of on-road and off-road (in various existing rights-of-way) configurations. On December 2, 2017, the Kitchener-Waterloo Record reported the local economy had already been stimulated through the construction of new buildings near the route, in both Kitchener–Waterloo and Cambridge. On-road sections keep the LRVs in dedicated lanes that do not mix with general traffic. In February 2017, after limitations in

350-671: A permanent museum for the city's heritage artifacts. Over 10,000 of the city's historical artifacts will be displayed in the City of Waterloo Museum. Waterloo's heritage collection has been mainly in storage over the past decade, with most of these artifacts coming from the closure of the Seagram Museum . The City of Waterloo Museum will be located between the new Bay store and food court entrance. Conestoga Mall supports green electricity, purchasing 30% of its common area electricity requirements from Bullfrog Power. Loblaw Companies , which operates

400-568: A staged implementation plan for its rapid transit system: Stage 1 – Implementation of LRT north of Fairview Park Mall and adapted Bus Rapid Transit south of Fairview Park Mall, including: The stage 1 route is 19 kilometres (12 mi) long. Stage 2 – Completion of a light rail transit system from Fairview Park in Kitchener to Ainslie Street in Cambridge. Commencement of Stage 2 to follow completion of Stage 1 as closely as possible. Out of

450-414: A standing capacity of 144 passengers. The body is constructed of five sections, in an accordion-like configuration to allow for sharp turns. It can be driven from either end. The top speed is 88 km/h (55 mph) but the average travel speed is unlikely to exceed 50 km/h (31 mph). The vehicles are numbered with a three-digit unit number in the 5xx series beginning with 501. This fleet number

500-399: A total of 14 by year end. The year end target was missed. On November 7, 2017, unpowered vehicle testing began on the tracks between Northfield Drive and Erb Street. An LRV was towed to check track clearances including along station platforms and to ensure continuous pantograph contact with the overhead electrical wiring. On December 19, 2017, GrandLinq had its first successful test of

550-482: A vote of 15–1. Cambridge mayor Doug Craig cast the dissenting vote. Other Cambridge-area representatives joined Craig in voting against subsequent motions on the service's staging, feeling that running only buses to that city does them a disservice. The Province of Ontario had promised to fund up to two thirds of the cost of the construction of a light rail or bus rapid transit system in Waterloo Region. However, in

SECTION 10

#1732855138791

600-403: Is completely road-separated. At street intersections, Ion light rail vehicles do not use the traditional automotive green-yellow-red traffic signals for road traffic, but rather the traditional two-aspect transit signals that show a vertical white bar for "go" and a horizontal white bar for "stop". Ion light rail vehicles have transit signal priority at intersections. Where a street crosses

650-440: Is displayed prominently on the end modules of each vehicle followed by a single letter to denote which end module the fleet number is on (e.g. 503A, 507B). The vehicles are being used for testing at the maintenance facility and all 19 km (12 mi) of the completed track. Production of the new vehicles was expected to begin in 2015 with the first to be delivered no later than August 2016 and all vehicles were to be received by

700-407: Is scheduled take about 46 minutes for an average speed of about 25 km/h (16 mph). As a comparison, the average speed of Toronto's light rail Line 5 Eglinton will be 28 kilometres per hour (17 mph) and the average speed of subway Line 2 Bloor–Danforth is 32 kilometres per hour (20 mph). Note that while Ion operates completely on the surface, Line 5 is half underground, and Line 2

750-435: Is still no specific timeline for replacing the aBRT service to Cambridge with light rail. On June 24, 2009, Regional Council approved LRT as the technology for rapid transit in Waterloo Region. Regional Council also approved a recommendation to implement the system in stages because ridership, development potential and capital and operating costs vary along the route. The light rail system was approved by Regional Council with

800-437: Is still running. Northbound Ion LRVs wait at Waterloo Public Square and southbound Ion LRVs wait at Northfield for the freight train to pass. The southbound return trip takes the reverse path and must return before Ion service starts at 5 am or they will have to wait until the next evening. This trip usually occurs Monday and Thursday nights but as with most freight schedules it can sometimes vary. Since freight cars are wider than

850-543: The Zehrs chain of grocery stores, has owned a large parcel of land to the southwest of Conestoga Mall. Despite much controversy with local citizens and the City of Waterloo, Loblaw planned to close the Conestoga Mall Zehrs and replace it with a much larger approximately 16,300-square-metre (175,000 sq ft) Real Canadian Superstore . In September 2008, Loblaw sold its land holding to Intelligent Mechatronics Systems,

900-736: The Ainslie Terminal. (At least one journalist has pointed out the similarity between this plan and the electric Grand River Railway of the early 1900s.) More detailed rendering of the route became available in October 2019, indicating elevated sections would be used to cross Fairway Road, the Grand River, Fountain Street and the Speed River, and the CP Rail line by Eagle Street. The Region approved

950-517: The Environmental Assessment also examined ten possible transport technologies, including monorails and subways. The EA as planned consisted of three phases: Phase 1: Determine a preferred transportation strategy from options such as road expansion, improved conventional transit, and rapid transit. Phase 1 was completed in July 2006. Phase 2: Phase 3: Design an implementation plan for

1000-563: The Ion Operations, Maintenance and Storage Facility (OMSF) located on Dutton Drive in Waterloo. The design of each of the stops was focused on an 'anchor wall', a 4 metres (13 ft) square panel subdivided into smaller tiles of glass, ceramic or stone; each station has a unique wall design based on the surrounding architecture, landmarks and social character. Ion light rail vehicles are in service between 5   am and midnight daily with

1050-535: The Ion tracks located either along a railway right of way or along the side of a cross road, the crossing is protected by traditional railway crossing signals: drop gates, flashing red lights and a bell. Crossings so protected are (from north to south) at Northfield Drive, Bearinger Road, Columbia Street, University Avenue, Seagram Drive and Erb Street in Waterloo, and at Ottawa Street, Mill Street, Hayward Avenue, Block Line Road, Courtland Avenue and Wilson Avenue in Kitchener. Canadian National Railway freight trains use

SECTION 20

#1732855138791

1100-602: The Kingston plant. Testing of vehicle 501 was scheduled to commence in May 2017 on the line between Northfield Drive and Silver Lake. In early April 2017, the Region expected to receive a second LRV in June or July, but that was postponed to late August or early September. By the beginning of October 2017, the second LRV had arrived. The schedule then called for delivery of another each 15 days, for

1150-528: The LRVs, there are gauntlet tracks at the southbound track of Ion stations along the Waterloo Spur to keep freight trains from striking the station platforms. To further protect station platforms and the Ion catenary system, there is a safety system to detect oversized freight cars and automatically stop the train using derailers . The detectors are located at Willow Street and just north of Northfield Drive. The route approved by Regional Council travels in

1200-552: The Regional Municipality began an Individual Environmental Assessment to study the feasibility of constructing a rapid transit line to provide higher-order public transit service to the Region and to encourage more compact urban growth along the corridor. The EA took a broader approach to studying possible routes and stations for the rapid transit line, examining several options such as utilizing existing tracks/roads and constructing new facilities. In keeping with legislation,

1250-424: The bus route serving Cambridge has been renamed "Ion Bus", and renumbered as 302. The first phase commenced operations on June 21, 2019, between the north end of Waterloo and the south end of Kitchener . A future extension of light rail to the downtown Galt area of Cambridge (Phase 2) is planned but construction may not begin on that line until 2028. In 2023, Ion LRT had an annual ridership of 4.3 million, and

1300-455: The challenge of the cramped core areas, and thus would also likely share space with traffic in core areas. In late 2011, planning was well underway and preparations were being made. In October, a property on Dutton Drive in Waterloo, bordering the rail-line corridor where the LRT is planned to be installed, was purchased to serve as a maintenance and storage yard for the system's LRVs. The site, which

1350-526: The end of 2016. On April 13, 2016, it was reported that Bombardier had informed the transit authority that delivery of the vehicles would be delayed. The region entered a joint agreement with Metrolinx and Bombardier in July 2013 for 14 LRVs, as well as an option to buy up to 14 more. Under the original agreement, the first vehicle was to be delivered no later than August 2016, and the final vehicle by December 2016. On May 20, 2016, Bombardier announced that to avoid further delays it would shift construction of

1400-663: The final bids, and approved by the Region's Planning and Works committee. Regional Council gave final approval on March 19, with financial close being made May 9. Ion rapid transit Ion , stylized as ION , is an integrated public transportation network in the Regional Municipality of Waterloo in Ontario , Canada. It is operated by Keolis and is part of the Grand River Transit (GRT) system, partially replacing GRT's Route 200 iXpress bus service. The section of

1450-408: The first "green" store in the company's portfolio - complete with environmentally-conscious measures such as solar panels, wind turbines, recycled carpet, and waterless urinals. The company also introduced higher end products such as Chanel cosmetics to serve Waterloo's growing affluence. Conestoga Mall donated 4,000 square feet (370 m ) in the new expansion to the City of Waterloo to establish

1500-421: The following month, on June 21, 2019; service across all of Grand River Transit, both LRT and bus, was to be free of charge for 11 days, until Canada Day. In August 2020, it was confirmed that part of a compensation package from Bombardier to settle shipping delays would be a fifteenth unit, provided free of charge, for the Ion fleet. It was delivered early March 2021. The Ion fleet is stored and maintained at

1550-669: The initiative and continued discussions with Provincial and Federal governments to obtain funding for the $ 790-million project. Light Rail Transit (LRT) was short-listed as the technology for the new rapid transit system. The Region decided on a staged approach, building light rail from Conestoga Mall to Fairview Park Mall , passing through Uptown Waterloo and Downtown Kitchener on the way. Adapted Bus Rapid Transit (aBRT) would be built from Fairview Park Mall to Ainslie Street terminal in Cambridge utilizing shoulder bypass lanes along Highways 8 and 401 during heavy traffic where speeds are often 40 km/h (25 mph) or less. As of June 2019, there

GrandLinq - Misplaced Pages Continue

1600-478: The introduction of the light rail service was significantly delayed. The total cost of the system was estimated at $ 818 million, but in December 2017, the overruns were estimated to total approximately $ 50 million. The Province was expected to provide $ 25 million of that amount. According to the Region of Waterloo, the Ion network is named after the atom , which it describes as being “always in motion”. In 2004,

1650-407: The mall. In June 2023 Primaris REIT announced an intention to acquire the mall for $ 270 million from Ivanhoé Cambridge . The transaction closed in July 2023. Conestoga Mall underwent a major $ 75 million redevelopment project. The project began in mid-2006, and was completed in the spring of 2010. Details of the project include a 130,000-square-foot (12,000 m ) expansion on the south end of

1700-627: The original route design came to light, a new preliminary preferred route plan was published. This would no longer use the CPR line south of Fairway; instead, it would travel to the east of it, along the River Rd extension and across Hwy 8; along King St into the Sportsworld area and under Hwy 401; along Shantz Hill Rd into Preston, and crossing the Speed River on a dedicated bridge. The subsequent plan, rejected by Cambridge City Council in July 2017, indicated that

1750-427: The projected service frequency will be approximately 7.5 minutes. In addition, a light rail line would be limited by the narrow main streets of key downtown areas. A feasible proposal raised by the Region for dealing with this challenge would be to have light rail vehicles (LRVs) share space with traffic within core areas, somewhat resembling the streetcar network of nearby Toronto. A bus rapid transit line would also face

1800-465: The property, a renovation and upgrade to the existing building, a new 700-seat food court with a new south end mall entrance, and a pedestrian-friendly façade. The redevelopment was also to include significant traffic improvements to the King Street entrance of the mall. The intersection of Conestogo Road and Kraus Drive were replaced with a roundabout at the City of Waterloo's request. A second entrance

1850-445: The purchase of 14 Flexity Freedom LRVs to form the system's initial fleet, with an option to purchase up to 14 more as the need arises. A further report on July 12, 2013, stated that the region would be purchasing 14 LRVs, with an option to buy 16 more. The 14 vehicles are estimated to cost $ 92.4 million, an average of $ 6.6 million per vehicle. The cost breakdown is: Each 30-metre (98 ft)-long, 30-tonne vehicle has 56 seats and

1900-742: The rapid transit system. In June 2008, the Province of Ontario announced a new expedited Transit Project Assessment Process (Ontario Regulation 231/08). In August 2008, the Region notified the Ministry of the Environment (MOE) to advise that it would transition from the Individual Environmental Assessment to the expedited process. For that reason, Phase 3 of the Individual EA would not be completed. On June 24, 2009, Regional Council approved

1950-404: The remaining $ 200–300 million required for the project to go ahead as planned. During public consultation for the project, concerns related to the light rail proposal focused on its relative service infrequency when compared with rapid transit systems in other cities (though it would still outperform the Region's best bus services in its overall service capacity, and the frequency of many routes);

2000-403: The schedule, the fourteenth and last LRV was expected to be delivered in February 2018 with full LRT service expected to start in spring 2018; however, this later became a June final delivery, with service start in December, then later to June 21, 2019. The final LRVs were delivered on December 6, 2018. At a Regional council meeting on May 8, 2019, it was announced that the service would launch

2050-572: The seven groups that showed an interest in the project, by December 18, 2013, three consortiums had submitted bids to design, build, finance, operate and maintain the Ion system: The winning bid was selected at a committee meeting on March 4, 2014. GrandLinq is the preferred bidder. The final approval of the GrandLinq bid came at a full council meeting on March 19, and financial close was made May 9. Conestoga Mall (Waterloo, Ontario) Conestoga Mall has over 130 stores and services. The mall has

GrandLinq - Misplaced Pages Continue

2100-403: The shared portion of the Waterloo Spur between 11   pm and 5   am. After crossing King Street, the northbound freight train joins the northbound Ion track at Caroline Street, cross over to the southbound Ion track just north of Erb Street and then continue north on the southbound track until just south of Northfield Drive. This train typically heads north just after 11pm while Ion service

2150-420: The summer of 2010, actual funding commitments from higher levels of government for the combined LRT and aBRT system were announced: $ 300 million from the province of Ontario, and $ 265 million (or up to 1/3 of the full cost) from the federal government. The provincial figure was disappointing to supporters, as the provincial government had previously promised to pay 2/3 of the cost. Regional council debated funding

2200-449: The system. A CBC report on December 21, 2017, indicated that the fourth vehicle was expected to be delivered before year-end. Six others were in final production and four were still in the assembly process. After the fourth vehicle was received in January, the first one was returned to Kingston for some additional work. At that time, five others were being tested by Bombardier. According to

2250-401: The system. In February, GrandLinq and two other groups, Tricity Transit System and Kitchener Waterloo Cambridge Transit Partners, were chosen as those which would be invited to submit proposals. In June the formal request for proposal was issued, and the three groups had until December to complete their bids. In March 2014, GrandLinq was identified as the preferred bidder in the staff report on

2300-523: The track would take Eagle St toward Hespeler, but to avoid conflicts with rail corridors and reduce traffic impacts at Eagle/Pinebush, would travel along the freight spur to Hespeler Rd. As previously, Hespeler Rd would be followed toward the Delta intersection, but to avoid traffic impacts it would veer east along the rail corridor behind Norfolk Ave, then transition to an abandoned railway corridor behind Grantham and Beverly Sts, before coming into downtown Galt near

2350-453: The vehicles for the Ion system from its Thunder Bay plant to another plant in Kingston, Ontario . The first vehicle, number 501 (its ends are labelled 501A and 501B), arrived in Waterloo Region on February 24, 2017. However, it was not ready for testing as its operating software was incomplete. By mid-March 2017, the second to fifth vehicles were seen by a CTV reporter as under construction in

2400-399: Was added to King Street in the form of a right in-right out intersection. The traffic upgrades were paid for by Ivanhoé Cambridge as a condition of the City of Waterloo issuing a building permit for the expansion of the shopping centre. The Bay (now " Hudson's Bay ") was moved slightly to the south and was completely rebuilt into a larger store. The new prototype Bay at Conestoga Mall was

2450-493: Was followed by a community building strategy to guide development, identify key destinations, and strengthen regional connections. The strategy, led by Urban Strategies Inc. of Toronto, consulted hundreds of individuals and stakeholders from Cambridge, Kitchener, and Waterloo. Construction began in August 2014 and service was expected to begin in late 2017; however, because of delays in the manufacture and delivery of rolling stock ,

2500-461: Was purchased for $ 6 million, will contain three buildings: the largest is 75,000 square feet (7,000 m ) and will house the operations centre and a repair shop; one will include a washing system; and the third is a 15,000 square feet (1,400 m ) wayside maintenance building that will house the repair truck fleet. On July 10, 2013, it was reported that a deal was finalized with Metrolinx to join its contract with Bombardier Transportation for