The Warren Railroad was a railroad in Warren County, New Jersey , that served as part of the Delaware, Lackawanna and Western Railroad 's mainline from 1856 to 1911.

#498501

59-567: The Oxford Tunnel , also known as the Van Nest Gap Tunnel , was one of seven tunnels built to complete the Warren Railroad , which formed part of Lackawanna Railroad 's 400-mile mainline. The tunnel was completed in 1862, and was retrofitted with a gauntlet track by 1900. The completion of the tunnel was delayed due to inconsistent funding, American Civil War -era technology, and issues with digging through gneiss . The construction of

118-511: A constant threat west of the tunnel, in Colby Cut. In recognition of this, a detector fence was installed west of Roseville Tunnel in 1950 to change trackside signals to red if rocks fell. The most serious rockslide to ever occur on the line, however, would take place within Armstrong Cut (just west of Johnsonburg) in 1941, closing the line for nearly a month, and causing trains to be rerouted via

177-785: A lease for the Morris & Essex Railroad (M&E), effective January 1, 1869. The DL&W then shifted their mainline off of CNJ to the M&;E with a new junction at Washington, New Jersey . While the Warren Railroad was straight from the DL&;W's former terminus at the Delaware River to the CNJ, its route to the M&E was circuitous. Additionally, the section between the Washington and Hampton (later called

236-644: A pioneering use of the material. The construction of the roadbed required the movement of millions of tons of fill material using techniques similar to those used on the Panama Canal . Operated through a subsidiary , Lackawanna Railroad of New Jersey, the Cut-Off remained in continual operation for 68 years, through the DL&W's 1960 merger with the Erie Railroad to form the Erie Lackawanna Railroad and

295-475: A time of historic infrastructure investment?" and Andover Mayor Tom Walsh is quoted as saying the decision was; "a kick in the teeth to the people who did all the work". Amtrak has placed the New York City-to-Scranton rail line on its proposed 2035 map. A federal study has examined the feasibility of an extension into northeastern Pennsylvania , possibly as far as Scranton , and Amtrak has released

354-458: Is known to have died of typhoid fever . The Cut-Off's reinforced concrete structures (73 in all), which consumed 266,885 cubic yards (204,048 m ) of concrete and 735 tons of steel, include underpasses , culverts , and the two large viaducts on the western end of the line. Some five million pounds (2,300 t) of dynamite were used to blast the cuts on the line. A total of 14,621,100 cubic yards (11,178,600 m ) of fill material

413-649: The Hampton Branch ) was deemed useless. The M&E was originally built to a gauge of 4 ft 10 in ( 1,473 mm ), but was converted to 4 ft  8 + 1 ⁄ 2  in ( 1,435 mm ) in July 1866. After the DL&W lease, a third rail was added for 66 miles (106 km) from Washington eastward to Hoboken from 1869-1870. DL&W's tracks from Scranton to Washington were converted to 4 ft  8 + 1 ⁄ 2  in ( 1,435 mm ) on May 27, 1876. The unused third rail on

472-718: The New Jersey Cut-Off , the Hopatcong-Slateford Cut-Off and the Blairstown Cut-Off ) was a rail line built by the Delaware, Lackawanna and Western Railroad (DL&W). Constructed from 1908 to 1911, the line was part of a 396-mile (637 km) main line between Hoboken, New Jersey , and Buffalo, New York . It ran west for 28.45 miles (45.79 km) from Port Morris Junction in Port Morris, New Jersey , near

531-685: The Pennsylvania Northeast Regional Railroad Authority . Subsequent federal studies conducted on the Cut-Off and the mainline into Pennsylvania found a need to restore passenger service. In 2011, after a nearly three-decade effort to reactivate the line, NJ Transit launched the $ 61 million Lackawanna Cut-Off Restoration Project. The first phase will link Port Morris Junction to Andover, New Jersey ( Andover station ), 7.3 miles (11.7 km) away. By December 2011, about 1 mile (1.6 km) of track had been installed from Port Morris Junction west to Stanhope, New Jersey . Work

590-455: The Warren Railroad required the completion of three bridges, two tunnels (the other tunnel being at Manuka Chuck), and cuts and fills. The tunnel was completed in September 1862. Later on, as train cars became larger, it became impossible to allow two tracks to fit through the tunnel. To address the issue, by 1900, a gauntlet track , which permits two tracks that closely overlap to pass through

649-463: The " Old Road " after the New Jersey Cut-Off opened) had numerous curves that restricted trains to 50 mph (80 km/h). The bigger operational problem, however, was caused by the two tunnels on the line: Manunka Chunk Tunnel, a 975-foot (297 m) twin-bore tunnel whose eastern approach occasionally flooded with heavy rains; and the 2,969-foot (905 m) single-bore Oxford Tunnel, which

SECTION 10

#1733084717499

708-541: The 28.45-mile (46 km) line evenly, the seven sections should have been just over four miles each, but that would have placed the Pequest Fill entirely within Section 3 and the two viaducts within Section 7.) The amount of work per mile varied; the largest share apparently went to David W. Flickwir, whose Section 3 included Roseville Tunnel and the eastern half of the Pequest Fill. DL&W chief engineer George G. Ray oversaw

767-617: The Blairstown Railway was a partial thoroughfare for the New York, Susquehanna & Western Railroad and the Lehigh & New England Railroad , the section from Delaware to Hainesburg was just a vestigial branch line known as the Delaware Branch, which was abandoned in 1928. The Belvidere Delaware Railroad (Bel Del) was extended north from Belvidere, New Jersey , to form a junction with

826-507: The CNJ abandoned operations in Pennsylvania, causing through freights to be run daily between Elizabeth, New Jersey , and Scranton, using the Cut-Off and the CNJ's High Bridge Branch . (This arrangement with the CNJ would end on April 1, 1976, with the creation of Conrail ). As such, when Penn Central closed its Maybrook, New York Yard in 1970, and its ex-New York, New Haven and Hartford Railroad Poughkeepsie Bridge burned on May 8, 1974,

885-466: The Cut-Off in 1958 in anticipation of the Erie merger. The westbound track was removed, leaving a four-mile (6.4 km) passing siding at Greendell and shorter sidings at Port Morris and Slateford. After the merger, most freight traffic shifted to the Erie's mainline through Port Jervis, New York . With the cessation of passenger service in 1970, the Cut-Off became relatively quiet for several years. In 1972,

944-415: The Cut-Off required fewer engines to pull eastbound freights up to the summit at Port Morris. For westbound freights, the challenge was keeping trains from going too fast. Initially, no speed limit existed on the Cut-Off, with engineers (both freight and passenger) being expected to exercise "good judgment". By the 1920s, however, most freights were restricted to 50 mph (80 km/h) or less, depending on

1003-504: The Cut-Off was completed. These workers were viewed with suspicion by the local populace in Warren and Sussex counties, with the town of Blairstown going as far as hiring a watchman at $ 40 per month for the duration of the project. Supervisory personnel and skilled laborers stayed in local hotels, boarding houses, or local farmhouses, usually at exorbitant rates ($ 1–2 per day) during the years of construction. With several thousand men working on

1062-403: The Cut-Off, making its last run on January 6, 1970. The only station on the Cut-Off at which mainline passenger trains would stop was Blairstown. Blairstown was also the first stop on westbound trains where passengers were permitted to disembark (i.e. westbound passengers boarding and detraining east of Blairstown were required to use suburban train service instead). This explains why Blairstown

1121-453: The Cut-Off. Over the years, Blairstown handled the most local freight. The Johnsonburg creamery, built in anticipation of the opening of the line, served local dairy farmers for years. Another creamery, an ice house , and a stock yard were built at Greendell. The final local shipment was shipped in 1978 by Conrail: cattle feed for a customer in Johnsonburg that was delivered to Greendell, as

1180-506: The EL's conveyance into Conrail in 1976. Conrail ceased operation of the Cut-Off in January 1979, removed the track in 1984, and sold the right-of-way to private developers. In 2001, the state of New Jersey acquired the right-of-way within its borders; the short section in Pennsylvania was eventually conveyed to the Pennsylvania Northeast Regional Railroad Authority . A project to restore service on

1239-517: The M&E was subsequently removed. The Lackawanna Cut-Off was built to minimize grades and curves, and to avoid the operational problems of the Warren Railroad. The Cut-Off was completed in 1911, becoming the new mainline of the DL&W. This relegated the Warren Railroad and the M&E line west of Port Morris Junction to a branch line known as the Lackawanna Old Road , starting the railroad's decline. In 1945, DL&W officially bought

SECTION 20

#1733084717499

1298-570: The NJ Transit Board of Directors on April 13, 2022, and a Notice to Proceed on the project was announced by NJ Transit on September 8, 2022. Commuter operations are expected to begin no earlier than 2026. In January of 2024, Amtrak unexpectedly dismissed future plans for a stop at Roseville Station in Andover, NJ. No reason for this was given publicly. Congressman Josh Gottheimer was quoted as saying; "Why would Amtrak limit transportation options at

1357-484: The Old Road needed to be replaced, it really wasn't until after 1905 that the railroad was in a position to take up the project in earnest. This led Truesdale to authorize teams of surveyors to map out potential replacement routes westward from Port Morris, New Jersey , to the Delaware River for what would be the railroad's largest project up until that time. During 1905–06, 14 routes were surveyed (labeled with letters of

1416-412: The Old Road shifted to the Cut-Off, effectively downgrading the older line to secondary status. The Cut-Off was built to permit unrestricted speeds for passenger trains of 70 mph (110 km/h) (heavier rail that was installed later allowed speeds to increase to 80 mph (130 km/h)). Sidings were built at Slateford, Hainesburg, Johnsonburg, Greendell, Roseville, and Port Morris; about 25% of

1475-538: The Old Road. The north side of Armstrong Cut was trimmed back to prevent further rockslides. The Cut-Off was a scenic highlight for passenger trains. Early in the 20th century, the DL&W's woman in white, Phoebe Snow , was featured in a poster that touted the new line and the Pequest Fill . At that time, and into the early diesel era (late 1940s), the Lackawanna Limited was the railroad's premier train. It

1534-491: The Warren Railroad at Manunka Chunk, which opened on May 16, 1864. The Pennsylvania Railroad operated to East Stroudsburg, Pennsylvania , via trackage rights. Passenger service ceased in 1952, and the tracks north of Belvidere to the junction were washed out by Hurricane Diane in 1955. The Lehigh and Hudson River Railway crossed beneath the Warren Railroad south of Bridgeville , without an interchange. Lackawanna Cut-Off The Lackawanna Cut-Off (also known as

1593-563: The Warren Railroad. In 1955 revenue freight service ended on the Hampton Branch; the last train to operate on the line was a work train in 1956. The line was officially abandoned in 1958. The grand Changewater truss bridge and Route 31 bridge in Hampton were removed in April 1959. Trackage remained intact until 1963 when Erie Lackawanna removed all of it. Hurricane Diane caused extensive damage to

1652-492: The Warren expensive to build, requiring a large amount of excavation, three large bridges, and two tunnels. DL&W began operating on the railway on May 28, 1856, from Delaware, New Jersey , to Hampton, and continuing over CNJ to Jersey City. DL&W formally leased the Warren Railroad in October 1857. The tracks were originally 6 ft ( 1,829 mm ) gauge, continuous with the DL&W's Pennsylvania tracks. A third rail

1711-473: The alphabet), including several that would have required long tunnels. On September 1, 1906, a route without tunnels was chosen. This New Road (Route "M") would run from the crest of the watershed at Lake Hopatcong at Port Morris Junction to 2 mi (3.2 km) south of the Delaware Water Gap on the Pennsylvania side of the Delaware River at Slateford Junction . At 28.45 miles (45.9 km),

1770-565: The clock during the summer of 1911 when construction fell behind schedule. Stations were built in Greendell , Johnsonburg and Blairstown ; the Greendell area was already being served by the nearby Lehigh & Hudson River Railroad in Tranquility. Interlocking towers were built at Port Morris Junction and Greendell , New Jersey, and Slateford Junction in Pennsylvania. The final cost of

1829-418: The east end of the Cut-Off to Andover, New Jersey , is to be complete in 2026. Amtrak is studying the possible restoration of passenger service over the route to Scranton, Pennsylvania . The line's origin involves two men who most likely never met: John I. Blair and William Truesdale . Blair built the DL&W's Warren Railroad , chartered in 1851 and completed in 1862, to provide a connection between

Oxford Tunnel - Misplaced Pages Continue

1888-524: The grades over the Pocono Mountains and EL's early-1960s severing of the Boonton Branch near Paterson, New Jersey . Conrail ran its final through freights via the Cut-Off on November 16, 1978, and used it to move a light engine from Croxton Yard to Scranton two days later. In early January 1979, the line was placed out of service and Port Morris Tower closed. Routine maintenance on the line ceased, and

1947-468: The line at Delaware and Manunka Chunk in 1955. The PRR junction was soon abandoned. The Old Road Branch was then single tracked from Washington to Delaware. Storm damage in 1968 near Oxford, New Jersey, led to the railroad's demise. All remaining trackage was removed by April 1970 between Washington and Delaware. Track remained in Delaware for some time after the line south to Washington was torn up because it

2006-412: The line would be about 11 mi (18 km) shorter than the 39.6-mile (63.7 km) Old Road. The new route would have only 15 curves – 42 fewer curves than the Old Road, the equivalent of more than four complete circles of curvature – which increased speeds and decreased running time – more so for freight, but for passenger trains as well. The ruling grade

2065-541: The line. Nevertheless, Conrail removed the tracks on the Cut-Off in 1984, and in the following year sold the right-of-way to two land developers: Jerry Turco and Burton Goldmeier. In 2001, the State of New Jersey acquired the right-of-way through eminent domain for $ 21 million. The short section in Pennsylvania was conveyed to the Monroe County Railroad Authority , which joined with Lackawanna County to become

2124-633: The mainlines of the DL&W in Pennsylvania and the Central Railroad of New Jersey (CNJ) in New Jersey. But when the Lackawanna-CNJ merger fell through and the Lackawanna merged with the Morris & Essex Railroad in New Jersey instead, the Warren Railroad became part of a circuitous patchwork of rail lines connecting two unanticipated merger partners. The 39-mile (63 km) route (later known as

2183-413: The original plans for the Cut-Off, and in fact much of the cut above the tunnel had already been blasted when in October 1909 unstable anticline rock was encountered, leading to a decision to abandon the cut and to blast what would become a 1,040-foot (320 m) tunnel instead. Contractor David W. Flickwir , whose section included Roseville Tunnel and the eastern half of the Pequest Fill, worked around

2242-548: The original reason for using the "Erie side" suddenly no longer existed. As a result, the EL looked to upgrade the "Scranton side", and by 1974 nearly all EL freights had been re-routed to the Scranton Division via the Cut-Off. After Conrail took over, existing labor contracts kept EL's freight schedule largely unchanged. The railroad replaced many rotted ties , returning it to better physical condition. But Conrail eventually shifted all freight traffic to other routes, citing

2301-463: The priority of the train and the type of locomotive and rail cars. By 1943, 131-pound-per-yard (65 kg/m) rail had been installed on the Cut-Off, which permitted fast freights to run at 60 mph (97 km/h) through the Erie Lackawanna years. After Conrail took over operations in 1976, the speed limit was decreased to 50 mph. Local freights served customers at all three stations on

2360-551: The project for over three years, the area all along the Cut-Off, and as far west as Portland, Pennsylvania, benefitted financially. As many as 30 workers may have lost their lives building the Cut-Off. Most of their names remain unknown because they were registered with their contractor by number only. In 1910, for example, five workers were killed in a single blasting mishap near Port Morris, one of several deadly accidents that involved dynamite. Other workers died in machinery or cable car accidents, or landslides. At least one worker

2419-510: The project was $ 11,065,512 in 1911. Adjusted for inflation, this sum would be $ 361,842,242 today . But to build such a project today would cost far more; one 1987 estimate put the modern pricetag at $ 1 billion or more. The first revenue train to operate on the Cut-Off under the new timetable that went into effect at 12:01 a.m. on December 24, 1911, was No. 15, a westbound passenger train that passed through Port Morris Junction at about 3:36 a.m. Most long-distance trains that traversed

Oxford Tunnel - Misplaced Pages Continue

2478-474: The project, although given the size and remote location of the project, Assistant Chief Engineer F.L. Wheaton was assigned the task of overseeing the construction in person. To accommodate the labor gangs, deserted farmhouses were converted to barracks, with tent camps providing additional shelter. These workers, many of whom came from Italy and other foreign countries or other parts of the U.S., were recruited and would move on to other projects after their work on

2537-429: The route contained additional sidings. With upwards of 50 trains a day, towermen often ordered freight trains to take a siding or even be rerouted over the Old Road. As traffic decreased, Hainesburg, Johnsonburg and Roseville sidings were altered or removed. The remaining sidings remained in use until 1979. Roseville Tunnel posed occasional problems, especially during the winter with snow and ice buildup. Rockslides were

2596-484: The siding at Johnsonburg no longer existed. There were two accidents on the Cut-Off: There were three other accidents that did not occur on the Cut-Off itself but indirectly involved it: The DL&W was one of the most profitable corporations in the U.S. when it built the Cut-Off. That profitability declined sharply after World War II , leading to the 1960 merger with the Erie Railroad . DL&W single-tracked

2655-595: The signal system was shut off. Scranton-Slateford freights continued running until 1980, when coal deliveries to the Metropolitan Edison power plant in Portland, Pennsylvania , shifted from the Scranton Division to the former Bangor & Portland Railway . Efforts to preserve the Cut-Off began shortly after Conrail ended service on it in 1979. An Amtrak inspection train ran on November 13 of that year, and counties in New Jersey and Pennsylvania made attempts to acquire

2714-491: The south end of Lake Hopatcong about 45 miles (72 km) west-northwest of New York City , to Slateford Junction in Slateford, Pennsylvania near the Delaware Water Gap . When it opened on December 24, 1911, the Cut-Off was considered a super-railroad, a state-of-the-art rail line, having been built using large cuts and fills and two large concrete viaducts , allowing what was considered high-speed travel at that time. It

2773-621: The tunnel together, was installed. The gauntlet track maximized the overhead and side clearances in the tunnel, but restricted the tunnel to a single-track section, creating a bottleneck on the line. In the end, the building of the Lackawanna Cut-Off would be the only solution that worked. In August 2018 there was a second major collapse in the tunnel. While still passable it is not without significant risk. 40°48′N 74°59′W  /  40.800°N 74.983°W  / 40.800; -74.983 Warren Railroad The Warren Railroad

2832-437: Was 11 miles (18 km) shorter than the Lackawanna Old Road , the rail line it superseded; it had a much gentler ruling gradient (0.55% vs. 1.1%); and it had 42 fewer curves, with all but one of those remaining permitting passenger train speeds of 70 mph (110 km/h) or more. It also had no railroad crossings at the time of its construction. All but one of the line's 73 structures were built of reinforced concrete ,

2891-404: Was added to CNJ's 4 ft  8 + 1 ⁄ 2  in ( 1,435 mm ) standard gauge track. When the railroad opened in 1856, the Van Nest Gap Tunnel was not yet completed, and a temporary track was used. The tunnel was completed in September 1862, and the temporary track removed. Merger talks between the DL&W and CNJ broke down and on December 10, 1868, the DL&W signed

2950-468: Was also modernized and renamed the Phoebe Snow , helping breathe freshness back into a passenger train program that had seen only modest improvements since the 1930s. The Phoebe Snow would run for 11 years as a DL&W train and then as an Erie Lackawanna train from 1963 until November 1966. The Lake Cities , ironically a former Erie Railroad train, became the last regularly scheduled passenger train on

3009-407: Was at its maximum height 110 feet (34 m) tall and was 3.12 miles (5.0 km) long, requiring 6,625,648 cubic yards (5,065,671 m ) of fill. Armstrong Cut was 100 feet (30 m) deep and 1 mile (1.6 km) long, mostly through solid rock. The line's deepest cut was Colby Cut (immediately west of what would become Roseville Tunnel ) at 130 feet (40 m) deep. The tunnel was not in

SECTION 50

#1733084717499

3068-435: Was chartered on February 12, 1851, by special act of the state of New Jersey, to provide a connection from the Delaware, Lackawanna & Western Railroad 's (DL&W) terminus at the Delaware River to Hampton, New Jersey , on the Central Railroad of New Jersey (CNJ), in anticipation of a merger between the two railroads. The railroad's date of organization was March 4, 1853, and construction began that June. Terrain made

3127-470: Was cut in half from 1.1% to 0.55%. The new line would also be built without railroad crossings to avoid collisions with automobiles and horse-drawn vehicles. Uncertain national economic conditions in 1907 delayed the official start of construction until August 1, 1908. The project was divided into seven sections, one for each contracting company. Sections 3–6 were 5 miles (8 km) each; Sections 1–2 and 7 were of varying lengths. (Theoretically, to divide

3186-467: Was delayed by various environmental and land-use issues, all of which have been resolved. As of 2022, about 4.25 miles (6.84 km) of rail, in three unconnected sections, has been laid between Port Morris and Lake Lackawanna , and most of the right-of-way between Port Morris Junction and the lake had been cleared of trees and debris. Work on the Roseville Tunnel, a two-year project, was approved by

3245-580: Was double-tracked in 1869 and reduced to gauntlet track in 1901. As more and more traffic moved over the line, Oxford Tunnel became the Lackawanna Railroad's worst bottleneck. Truesdale became DL&W president on March 2, 1899 with a mandate to upgrade the entire 900-mile (1,450 km) railroad. Early on, the railroad focused on increasing freight capacity by using larger locomotives and cars, as well as strengthening bridges to handle these larger loads. Although Truesdale recognized early on that

3304-800: Was later joined by the Pocono Express , the Owl , and the Twilight . While the Lackawanna only operated mainline passenger trains between Hoboken, New Jersey, and Buffalo, New York, passengers could transfer to and from other railroads at Buffalo. For example, the Nickel Plate offered through sleeper service to St. Louis and Kansas City, Missouri, via the Lackawanna. In 1949, the Lackawanna began modernizing its mainline passenger coaches. The railroad had already begun replacing steam engines with diesels in 1946, starting with mainline passenger trains. The Lackawanna Limited

3363-521: Was needed for coal train back ups from the Portland power plant. Track was later shortened to the truss bridge over the Delaware River by 1980. Until about 15 years ago, coal trains still backed out on the truss bridge. Two connections from other railroads were made to the Warren Railroad. The Blairstown Railway opened in 1877, from a connection to the Warren Railroad in Delaware to Blairstown . While

3422-524: Was required for the project, more than could be obtained from the project's cuts. This forced the DL&W to purchase 760 acres (310 ha) of farmland for borrow pits . Depending on the fill size, material was dumped from trains that backed out onto track on wooden trestles or suspended on cables between steel towers. During construction, several foreign governments sent representatives on inspection tours to study these new techniques. The Pequest Fill extended west of Andover to Huntsville, New Jersey . It

3481-444: Was the first stop listed on the destination board at the boarding gate at Hoboken for trains travelling via Scranton. In later years, Blairstown had a somewhat unusual facet of operation: any trains arriving after the station agent went home for the night would automatically activate the station platform lights as the train entered the signal block. This practice was abandoned after passenger service ended. Besides cutting travel time,