Misplaced Pages

Tunnel boring machine

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

A tunnel boring machine ( TBM ), also known as a "mole" or a "worm", is a machine used to excavate tunnels . Tunnels are excavated through hard rock, wet or dry soil, or sand , each of which requires specialized technology.

#127872

53-914: Tunnel boring machines are an alternative to drilling and blasting (D&B) methods and "hand mining". TBMs limit the disturbance to the surrounding ground and produce a smooth tunnel wall. This reduces the cost of lining the tunnel, and is suitable for use in urban areas. TBMs are expensive to construct, and larger ones are challenging to transport. These fixed costs become less significant for longer tunnels. TBM-bored tunnel cross-sections range from 1 to 17.6 meters (3.3 to 57.7 ft) to date. Narrower tunnels are typically bored using trenchless construction methods or horizontal directional drilling rather than TBMs. TBM tunnels are typically circular in cross-section although they may be u-shaped, horseshoes, square or rectangular. Tunneling speeds increase over time. The first TBM peaked at 4 meters per week. This increased to 16 meters per week four decades later. By

106-614: A boring diameter of 6.67 m (21.9 ft). The medium was water saturated sandy mudstone, schistose mudstone, highly weathered mudstone as well as alluvium. It achieved a maximum advance rate of more than 345 m (1,132 ft) per month. The world's largest hard rock TBM, known as Martina , was built by Herrenknecht AG . Its excavation diameter was 15.62 m (51.2 ft), total length 130 m (430 ft); excavation area of 192 m (2,070 sq ft), thrust value 39,485 t, total weight 4,500 tons, total installed capacity 18 MW. Its yearly energy consumption

159-457: A leading shield that advances with the cutting head and a trailing shield that acts as a gripper. The two shields can move axially relative to each other (i.e., telescopically) over a limited distance. The gripper shield anchors the TBM so that pressure can be applied to the cutter head while simultaneously the concrete lining is being constructed. In hard rock with minimal ground water, the area around

212-435: A plug to form in the screw. The cutter head is filled with pressurised slurry, typically made of bentonite clay that applies hydrostatic pressure to the face. The slurry mixes with the muck before it is pumped to a slurry separation plant, usually outside the tunnel. Slurry separation plants use multi-stage filtration systems that separate spoil from slurry to allow reuse. The degree to which slurry can be 'cleaned' depends on

265-476: A rotating drum with metal tines on its outer surface, or a rotating circular plate covered with teeth, or revolving belts covered with metal teeth. However, these TBMs proved expensive, cumbersome, and unable to excavate hard rock; interest in TBMs therefore declined. Nevertheless, TBM development continued in potash and coal mines, where the rock was softer. A TBM with a bore diameter of 14.4 m (47 ft 3 in)

318-402: A single cylindrical shield after the cutting head. A permanent concrete lining is constructed immediately after the shield, and the TBM pushes off the lining to apply force to the cutter head. Because this pushing cannot be done while a next ring of lining is being constructed, the single-shield TBM operates in alternating cutting and lining modes. Double Shield (or telescopic shield) TBMs have

371-799: A speed and safety not previously possible. The Channel Tunnel , the Thames Water Ring Main , sections of the London Underground , and most new metro tunnels completed in the last 20 years worldwide were excavated using this method. EPB has historically competed with the slurry shield method (see below), where the slurry is used to stabilize the tunnel face and transport spoil to the surface. EPB TBMs are mostly used in finer ground (such as clay) while slurry TBMs are mostly used for coarser ground (such as gravel). Slurry shield machines can be used in soft ground with high water pressure or where granular ground conditions (sands and gravels) do not allow

424-765: Is a commune in the Pas-de-Calais department on the northern coast of France on the English Channel . The name is of Flemish origin, meaning hole or gap in the sand. Sangatte is the location for the Channel Tunnel 's French cooling station, its British counterpart being at Samphire Hoe . In addition, it is the French end-point for the HVDC Cross-Channel , the connection between the UK and French electricity grids. Sangatte

477-546: Is a smaller equivalent to a general tunnelling shield and generally bore tunnels of 1 to 1.5 meters (3.3 to 4.9 ft), too small for operators to walk in. Behind all types of tunnel boring machines, in the finished part of the tunnel, are trailing support decks known as the backup system, whose mechanisms can include conveyors or other systems for muck removal; slurry pipelines (if applicable); control rooms; electrical, dust-removal and ventilation systems; and mechanisms for transport of pre-cast segments. Urban tunnelling has

530-401: Is also the landing location of Supermarine Spitfire Mark 1a N3200 of No. 19 Squadron RAF , which was forced to land at the beach after receiving damage to its radiator from shots fired by a Messerschmitt Bf 109 of JG 2 during Operation Dynamo on 26 May 1940, having shot down a Junkers Ju 87 shortly beforehand to protect the evacuating soldiers at Dunkirk . The plane was recovered from

583-449: Is often known as a rock cut . Drilling and blasting currently utilizes many different varieties of explosives with different compositions and performance properties. Higher velocity explosives are used for relatively hard rock in order to shatter and break the rock, while low velocity explosives are used in soft rocks to generate more gas pressure and a greater heaving effect. For instance, an early 20th-century blasting manual compared

SECTION 10

#1733085091128

636-476: Is still used in the construction of tunnels, such as in the construction of the Lötschberg Base Tunnel . The decision whether to construct a tunnel using a TBM or using a drill and blast method includes a number of factors. Tunnel length is a key issue that needs to be addressed because large TBMs for a rock tunnel have a high capital cost, but because they are usually quicker than a drill and blast tunnel

689-463: The Alps , Maus had it built in 1846 in an arms factory near Turin . It consisted of more than 100 percussion drills mounted in the front of a locomotive-sized machine, mechanically power-driven from the entrance of the tunnel. The Revolutions of 1848 affected the funding, and the tunnel was not completed until 10 years later, by using less innovative and less expensive methods such as pneumatic drills . In

742-622: The Mersey River . The Hudson River Tunnel was constructed from 1889 to 1904 using a Greathead shield TBM. The project used air compressed to 2.4 bar (35 psi) to reduce cave-ins. However, many workers died via cave-in or decompression sickness. During the late 19th and early 20th century, inventors continued to design, build, and test TBMs for tunnels for railroads, subways, sewers, water supplies, etc. TBMs employing rotating arrays of drills or hammers were patented. TBMs that resembled giant hole saws were proposed. Other TBMs consisted of

795-475: The Fréjus Rail Tunnel, by using less ambitious methods). Wilson's machine anticipated modern TBMs in the sense that it employed cutting discs, like those of a disc harrow , which were attached to the rotating head of the machine. In contrast to traditional chiseling or drilling and blasting, this innovative method of removing rock relied on simple metal wheels to apply a transient high pressure that fractured

848-489: The Soviet Union was the leader in total volume with 2.7 billion kg of explosives consumed (13 m per capita), and Australia had the highest per capita explosives consumption that year with 45 m per capita. As the name suggests, drilling and blasting works as follows: The positions and depths of the holes (and the amount of explosive each hole receives) are determined by a carefully constructed pattern, which, together with

901-521: The Tuen Mun Chek Lap Kok link in Hong Kong. TBMs typically consist of a rotating cutting wheel in front, called a cutter head, followed by a main bearing, a thrust system, a system to remove excavated material (muck), and support mechanisms. Machines vary with site geology, amount of ground water present, and other factors. Rock boring machines differ from earth boring machines in the way they cut

954-451: The UK government, Nicolas Sarkozy (then Minister of the Interior), ordered its closure in 2002. There were riots in 2001 and 2002, the year the camp closed. General Councillor for Calais-Nord-Ouest (2004 → 2006) Passed away in service (September 19th 2024) Vice-president of CA Grand Calais Terres et Mers Reelected for 2014-2020 term ,, Relected for 2020-2026 term ,, In

1007-517: The United States, the first boring machine to have been built was used in 1853 during the construction of the Hoosac Tunnel in northwest Massachusetts. Made of cast iron, it was known as Wilson's Patented Stone-Cutting Machine , after inventor Charles Wilson. It drilled 3 meters (10 ft) into the rock before breaking down (the tunnel was eventually completed more than 20 years later, and as with

1060-470: The caisson, requiring workers to be medically cleared as "fit to dive" and able to operate pressure locks. Open face soft ground TBMs rely on the excavated ground to briefly stand without support. They are suitable for use in ground with a strength of up to about 10 MPa (1,500 psi) with low water inflows. They can bore tunnels with cross-section in excess of 10 m (30 ft). A backactor arm or cutter head bore to within 150 mm (6 in) of

1113-470: The construction of a tunnel under the English Channel and the British Parliament supported a trial run using English's TBM. Its cutting head consisted of a conical drill bit behind which were a pair of opposing arms on which were mounted cutting discs. From June 1882 to March 1883, the machine tunneled, through chalk, a total of 1,840 m (6,036 ft). A French engineer, Alexandre Lavalley , who

SECTION 20

#1733085091128

1166-639: The construction of the South Eastern Railway . About 400,000 cubic yards of chalk was displaced in an exercise that it was estimated saved the company six months time and £7,000 in expense. While drilling and blasting saw limited use in pre-industrial times using gunpowder (such as with the Blue Ridge Tunnel in the United States, built in the 1850s), it was not until more powerful (and safer) explosives , such as dynamite (patented 1867), as well as powered drills were developed, that its potential

1219-400: The correct timing of the individual explosions, will guarantee that the tunnel will have an approximately circular cross-section. During operation, blasting mats may be used to contain the blast, suppress dust and noise, for fly rock prevention and sometimes to direct the blast. As a tunnel or excavation progresses the roof and side walls need to be supported to stop the rock falling into

1272-439: The cutter head and extraction screw to ensure that the muck is sufficiently cohesive to maintain pressure and restrict water flow. Like some other TBM types, EPB's use thrust cylinders to advance by pushing against concrete segments. The cutter head uses a combination of tungsten carbide cutting bits, carbide disc cutters, drag picks and/or hard rock disc cutters. EPB has allowed soft, wet, or unstable ground to be tunneled with

1325-437: The cutter head of a TBM can be unpressurized, as the exposed rock face can support itself. In weaker soil, or when there is significant ground water, pressure must be applied to the face of the tunnel to prevent collapse and/or the infiltration of ground water into the machine. Earth pressure balance (EPB) machines are used in soft ground with less than 7 bar (100 psi) of pressure. It uses muck to maintain pressure at

1378-434: The cutter head to support the walls until permanent tunnel support is constructed further along the machine. The stability of the walls also influences the method by which the TBM anchors itself in place so that it can apply force to the cutting head. This in turn determines whether the machine can bore and advance simultaneously, or whether these are done in alternating modes. Gripper TBMs are used in rock tunnels. They forgo

1431-482: The cutting discs would travel over almost all of the rock face that was to be removed. The first TBM that tunneled a substantial distance was invented in 1863 and improved in 1875 by British Army officer Major Frederick Edward Blackett Beaumont (1833–1895); Beaumont's machine was further improved in 1880 by British Army officer Major Thomas English (1843–1935). In 1875, the French National Assembly approved

1484-506: The edge of the shield. After a boring cycle, the shield is jacked forward to begin a new cycle. Ground support is provided by precast concrete, or occasionally spheroidal graphite iron (SGI) segments that are bolted or supported until a support ring has been added. The final segment, called the key, is wedge-shaped, and expands the ring until it is tight against the ground. TBMs range diameter from 1 to 17 meters (3 to 56 ft). Micro tunnel shield TBMs are used to construct small tunnels, and

1537-399: The effects of black powder to that of a wedge, and dynamite to that of a hammer. The most commonly used explosives in mining today are ANFO based blends due to lower cost than dynamite . Before the advent of tunnel boring machines (TBMs), drilling and blasting was the only economical way of excavating long tunnels through hard rock, where digging is not possible. Even today, the method

1590-459: The end of the 19th century, speeds had reached over 30 meters per week. 21st century rock TBMs can excavate over 700 meters per week, while soil tunneling machines can exceed 200 meters per week. Speed generally declines as tunnel size increases. The first successful tunnelling shield was developed by Sir Marc Isambard Brunel to excavate the Thames Tunnel in 1825. However, this

1643-429: The excavation. The philosophy and methods for rock support vary widely but typical rock support systems can include: Typically a rock support system would include a number of these support methods, each intended to undertake a specific role in the rock support such as the combination of rock bolting and shotcrete. Sangatte Sangatte ( French pronunciation: [sɑ̃ɡat] ; West Flemish : Zandgat )

Tunnel boring machine - Misplaced Pages Continue

1696-484: The explosive. The first to use this method for underwater blasting was Charles Pasley who employed it in 1839 to break up the wreck of the British warship HMS Royal George which had become a shipping hazard at Spithead . An early major use of blasting to remove rock occurred in 1843 when the British civil engineer William Cubitt used 18,000 lbs of gunpowder to remove a 400-foot-high chalk cliff near Dover as part of

1749-424: The hole during this process was then removed and replaced with a train of gunpowder. This train was ignited by a slow match , often consisting simply of brown paper smeared with grease, intended to burn long enough to allow the person who fires it enough time to reach a place of safety. The uncertainty of this method led to many accidents and various measures were introduced to improve safety for those involved. One

1802-402: The price per metre of tunnel is lower. This means that shorter tunnels tend to be less economical to construct with a TBM and are therefore usually constructed by drill and blast. Managing ground conditions can also have a significant effect on the choice with different methods suited to different hazards in the ground. The use of explosives in mining goes back to the year 1627, when gunpowder

1855-475: The prize offered by the Daily Mail . The crossing took 37 minutes in his aeroplane, Blériot XI , built in collaboration with Raymond Saulnier . It was powered by a 3-cylinder 25 horsepower (19 kW) engine . At the western end of the beach, a statue of the French aviator Hubert Latham overlooks the sea. Latham was another pioneering cross-channel pilot whose earlier attempt on 19 July had failed. Sangatte

1908-439: The project must accommodate measures to mitigate any detrimental effects to other infrastructure. Drilling and blasting Drilling and blasting is the controlled use of explosives and other methods, such as gas pressure blasting pyrotechnics, to break rock for excavation . It is practiced most often in mining , quarrying and civil engineering such as dam , tunnel or road construction. The result of rock blasting

1961-405: The relative particle sizes of the muck. Slurry TBMs are not suitable for silts and clays as the particle sizes of the spoil are less than that of the bentonite. In this case, water is removed from the slurry leaving a clay cake, which may be polluted. A caisson system is sometimes placed at the cutting head to allow workers to operate the machine, although air pressure may reach elevated levels in

2014-470: The rock. In 1853, the American Ebenezer Talbot also patented a TBM that employed Wilson's cutting discs, although they were mounted on rotating arms, which in turn were mounted on a rotating plate. In the 1870s, John D. Brunton of England built a machine employing cutting discs that were mounted eccentrically on rotating plates, which in turn were mounted eccentrically on a rotating plate, so that

2067-539: The sand at Sangatte in 1986, and restoration work commenced in 2000, which continued until 2014 when works completed, the aircraft having been repaired to a fully airworthy state. Sangatte was the location of a refugee camp set up by the French Red Cross in 1999 as a result of an influx of migrants attempting to travel to the United Kingdom. They were mainly from Afghanistan, Iraq and Kosovo. Under pressure from

2120-587: The special requirement that the surface remain undisturbed, and that ground subsidence be avoided. The normal method of doing this in soft ground is to maintain soil pressures during and after construction. TBMs with positive face control, such as earth pressure balance (EPB) and slurry shield (SS), are used in such situations. Both types (EPB and SS) are capable of reducing the risk of surface subsidence and voids if ground conditions are well documented. When tunnelling in urban environments, other tunnels, existing utility lines and deep foundations must be considered, and

2173-587: The tunnel face. Main Beam machines do not install concrete segments behind the cutter head. Instead, the rock is held up using ground support methods such as ring beams, rock bolts, shotcrete , steel straps, ring steel and wire mesh. Depending on the stability of the local geology, the newly formed walls of the tunnel often need to be supported immediately after being dug to avoid collapse, before any permanent support or lining has been constructed. Many TBMs are equipped with one or more cylindrical shields following behind

Tunnel boring machine - Misplaced Pages Continue

2226-401: The tunnel face. The muck (or spoil ) is admitted into the TBM via a screw conveyor . By adjusting the rate of extraction of muck and the advance rate of the TBM, the pressure at the face of the TBM can be controlled without the use of slurry . Additives such as bentonite , polymers and foam can be injected ahead of the face to stabilize the ground. Such additives can separately be injected in

2279-410: The tunnel, the way they provide traction to support the boring activity, and in the way they support the newly formed tunnels walls. Shielded TBMs are typically used to excavate tunnels in soil. They erect concrete segments behind the TBM to support the tunnel walls. The machine stabilizes itself in the tunnel with hydraulic cylinders that press against the shield, allowing the TBM to apply pressure at

2332-410: The use of a shield and instead push directly against the unreinforced sides of the tunnel. Machines such as a Wirth machine can be moved only while ungripped. Other machines can move continuously. At the end of a Wirth boring cycle, legs drop to the ground, the grippers are retracted, and the machine advances. The grippers then reengage and the rear legs lift for the next cycle. A single-shield TBM has

2385-607: Was about 62 GWh. It is owned and operated by the Italian construction company Toto S.p.A. Costruzioni Generali (Toto Group) for the Sparvo gallery of the Italian Motorway Pass A1 ("Variante di Valico A1"), near Florence. The same company built the world's largest-diameter slurry TBM , excavation diameter of 17.6 meters (58 ft), owned and operated by the French construction company Dragages Hong Kong (Bouygues' subsidiary) for

2438-534: Was also a Suez Canal contractor , used a similar machine to drill 1,669 m (5,476 ft) from Sangatte on the French side. However, despite this success, the cross-Channel tunnel project was abandoned in 1883 after the British military raised fears that the tunnel might be used as an invasion route. Nevertheless, in 1883, this TBM was used to bore a railway ventilation tunnel — 2 m (7 ft) in diameter and 2.06 km (6,750 ft) long — between Birkenhead and Liverpool , England, through sandstone under

2491-572: Was first used in place of mechanical tools in the Hungarian (now Slovak ) town of Banská Štiavnica . The innovation spread quickly throughout Europe and the Americas. The standard method for blasting rocks was to drill a hole to a considerable depth and deposit a charge of gunpowder at the further end of the hole and then fill the remainder of the hole with clay or some other soft mineral substance, well rammed, to make it as tight as possible. A wire laid in

2544-748: Was fully realised. Drilling and blasting was successfully used to construct tunnels throughout the world, notably the Fréjus Rail Tunnel , the Gotthard Rail Tunnel , the Simplon Tunnel , the Jungfraubahn and even the longest road tunnel in the world, Lærdalstunnelen , are constructed using this method. In 1990, 2.1 billion kg of commercial explosives were consumed in the United States (12 m per capita), representing an estimated expenditure of 3.5 to 4 billion 1993 dollars on blasting. In this year

2597-473: Was manufactured by The Robbins Company for Canada's Niagara Tunnel Project . The machine was used to bore a hydroelectric tunnel beneath Niagara Falls . The machine was named "Big Becky" in reference to the Sir Adam Beck hydroelectric dams to which it tunnelled to provide an additional hydroelectric tunnel. An earth pressure balance TBM known as Bertha with a bore diameter of 17.45 meters (57.3 ft)

2650-503: Was only the invention of the shield concept and did not involve the construction of a complete tunnel boring machine, the digging still having to be accomplished by the then standard excavation methods. The first boring machine reported to have been built was Henri Maus 's Mountain Slicer . Commissioned by the King of Sardinia in 1845 to dig the Fréjus Rail Tunnel between France and Italy through

2703-524: Was produced by Hitachi Zosen Corporation in 2013. It was delivered to Seattle , Washington , for its Highway 99 tunnel project . The machine began operating in July 2013, but stalled in December 2013 and required substantial repairs that halted the machine until January 2016. Bertha completed boring the tunnel on April 4, 2017. Two TBMs supplied by CREG excavated two tunnels for Kuala Lumpur 's Rapid Transit with

SECTION 50

#1733085091128

2756-431: Was replacing the iron wire, by which the passage for the gunpowder is formed, with one of copper, to eliminate sparking that could ignite the powder prematurely. Another was the use of a safety fuse . This consisted of small train of gunpowder inserted in a water-proof cord, which burns at a steady and uniform rate. This in turn was later replaced by a long piece of wire that was used to deliver an electric charge to ignite

2809-579: Was the landing point of the world's first operational underwater telegraph cable, laid across the Channel by the Submarine Telegraph Company in 1851 between South Foreland and Sangatte. 'Blériot-Plage' is named to commemorate Louis Blériot who, on 25 July 1909, was the first person to fly across the English Channel . He flew from the beach at Sangatte to the White Cliffs of Dover , to claim

#127872