Misplaced Pages

MPAN

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

A Meter Point Administration Number , also known as MPAN , Supply Number or S-Number , is a 21-digit reference used in Great Britain to uniquely identify electricity supply points such as individual domestic residences. The system was introduced in 1998 to aid creation of a competitive environment for the electricity companies, and allows consumers to switch their supplier easily as well as simplifying administration. Although the name suggests that an MPAN refers to a particular meter, an MPAN can have several meters associated with it, or indeed none where it is an unmetered supply. A supply receiving power from the network operator ( DNO ) has an import MPAN, while generation and microgeneration projects feeding back into the DNO network are given export MPANs.

#741258

67-491: MPAN is an acronym that can refer to: Meter Point Administration Number , a reference number used in Great Britain to uniquely identify electricity supply points Mitochondrial membrane protein-associated neurodegeneration , a rare disease that is a form of neurodegeneration with brain iron accumulation MPAN (TV channel) , Montana Public Affairs Network Topics referred to by

134-599: A Glaswegian industrialist, to solve the problem of Britain's inefficient and fragmented electricity supply industry. Weir consulted Merz, and the result was the Electricity (Supply) Act 1926 , which recommended that a "national gridiron " supply system be created. The 1926 Act created the Central Electricity Board , which set up the UK's first synchronised, nationwide AC grid, running at 132 kV, 50 Hz. The grid

201-630: A grid services market. "Dynamic Containment" started in October 2020, initially priced at £17 per MW per hour, and Dynamic Regulation (DR) started in April 2022. Consumers of electricity are split into two categories: half-hourly metered (HH) and non-half-hourly metered (NHH). Customers whose peak demand is sufficiently high are obliged to have a HH meter, which, in effect, takes a meter reading every 30 minutes. The rates at which charges are levied on these customers' electricity suppliers therefore varies 17,520 times

268-523: A meter serial number . Although it is common for an MPAN to be associated with one meter serial number, in some cases there is a many-to-many relationship. For example, one meter could be associated with both an import and an export MPAN, or one MPAN could be measured by three separate meters. It is possible for small predictable supplies to be unmetered. Examples are street lights, traffic signals, signs, bollards, telephone kiosks, CCTV and advertising displays. For an item of equipment to be connected to

335-415: A stretch target to be carbon neutral or negative by 2033, well ahead of the UK's national target to achieve this by 2050. It also aims to have the capability to be 'zero carbon' as early as 2025, meaning that if energy suppliers are able to produce sufficient green power, the grid could theoretically run without any greenhouse gas emissions at all (i.e. no carbon capture or offsetting would be needed as

402-481: A (non-leap) year. The TNUoS charges for a HH metered customer are based on their demand during three half-hour periods of greatest demand between November and February, known as the Triad. Due to the nature of electricity demand in the UK, the three Triad periods always fall in the early evening, and must be separated by at least ten clear working days. The TNUoS charges for a HH customer are simply their average demand during

469-571: A 500 kV scheme. Design work was started and in order to meet the programme for 1965 it was necessary for the contract engineering for the first projects to run concurrently with the design. One of these projects was the West Burton 400 kV Indoor Substation, the first section of which was commissioned in June 1965. From 1965, the grid was partly upgraded to 400 kV, beginning with a 150-mile (240 km) line from Sundon to West Burton , to become

536-405: A better solution was sought. Consideration was given to 400 kV and 500 kV schemes: both gave a sufficient margin for future expansion. The decision in favour of a 400 kV system was made for two main reasons. Firstly the majority of the 275 kV lines could be uprated to 400 kV, and secondly it was envisaged that operation at 400 kV could begin in 1965 compared with 1968 for

603-448: A half-hourly basis. The Metered Supply Point (MSP) is the point at which the meter measuring a customer's consumption is located. It is thus also the point at which either the distribution network operator 's supply, or the building network operator's lateral cable, terminates and the customer's equipment begins. In order to firmly establish a supply's MSP, the MPAN needs to be associated with

670-452: A half-hourly compliant meter to be installed. Since 2003, it has been possible for microgeneration projects, with a capacity of 30 kW or below, to have a non-half-hourly meter to measure export back into the distribution network. Uptake was slow, with the first microgeneration export MPAN being issued in June 2005. Some suppliers may not bother to register the export MPAN in MPAS as the revenue

737-410: A maximum rate of 75 MW during the year would still be charged for the full 100 MW of TEC. In some cases, there are negative TNUoS tariffs. These generators are paid an amount based on their peak net supply over three proving runs over the course of the year. This represents the reduction in costs caused by having a generator close to the centre of demand of the country. National Grid uses

SECTION 10

#1732883532742

804-445: A meter administrator who will use daily data from a photo-electric control unit (PECU) array which is then used to calculate the energy consumption. A PECU array is a device that holds a representative number of the photocells that authority uses on their street lights or traffic signals. By trading energy as unmetered half-hourly the authority will accurately pay for the energy consumed by their declared unmetered equipment, and because

871-425: A meter may have, such as a single rate, day/night split, or a seasonal time of day. The Line Loss Factor Class or LLFC is an alphanumeric code used to identify the related Distribution Use of System (DUoS) charges for the MPAN. The figure reflects both the amount of distribution infrastructure used to supply the exit point and the amount of energy lost through heating of cables, transformers, etc. The MPAN core

938-652: A new non-lattice design of electricity pylon, the T-pylon, was built near East Huntspill , Somerset for the new 35 mile Hinkley Point C to Avonmouth connection. In 2023, the National Grid began removing equipment from China's NARI Technology over national security concerns. The contiguous synchronous grid covers England (including the Isle of Wight ), Scotland (including some of the Scottish islands such as Orkney , Skye and

1005-606: A specific geographic area, there are also independent distribution network operators (IDNOs). These own and operate electricity distribution networks which are mostly network extensions connected to the existing distribution network, e.g. to serve new housing developments. Scottish Hydro Electric Power Distribution also provide distribution services in South Scotland as an IDNO and Southern Electric Power Distribution provide IDNO services in all other England and Wales areas. Other IDNOs have no "base" area. The supply identified by

1072-527: A surplus of cheap low-grade fuel and adequate supplies of cooling water, but these sites did not coincide with the load centres. West Burton 's 4 × 500 MW machines, in the Nottinghamshire coalfield near the River Trent , is an example. These developments shifted the emphasis on the transmission system from interconnection to bulk power transfers from the generation areas to the load centres, such as

1139-444: Is a website that allows users and authorised industry parties to search for supply details (past and present) using such things as the 13-digit MPAN bottom line number, the meter serial number or the postcode. The user can determine a wide range of data relating to the supply including the full address, meter details, the current energisation status and also the appointed parties (i.e. the supplier, distributor, MOP, DC and DA). The site

1206-422: Is charged separately). The grid also charges an annual fee to cover the cost of generators, distribution networks and large industrial users connecting. Triad charges encourage users to cut load at peak periods; this is often achieved by using diesel generators. Such generators are also routinely used by National Grid. If the total TNUoS or Triad receipts (say £15,000/MW·year × 50,000 MW = £750 million/year)

1273-448: Is completed, the site's storage capacity will be 266 MWh. National Grid is responsible for contracting short term generating provision to cover demand prediction errors and sudden failures at power stations. This covers a few hours of operation giving time for market contracts to be established to cover longer term balancing. The grid frequency is normally maintained within 49.8 and 50.2 Hz. Frequency-response reserves act to keep

1340-526: Is different from Wikidata All article disambiguation pages All disambiguation pages Meter Point Administration Number The equivalent for gas supplies is the Meter Point Reference Number and the water/wastewater equivalent for non-household customers is the Supply Point ID . An MPAN is commonly separated into two sections: the core and the top line data. The core is

1407-668: Is divided by the total number of units delivered by the UK generating system in a year (the total number of units sold – say 360 terawatt-hours (1.3 EJ). ), then a crude estimate can be made of transmission costs, and one gets the figure of around 0.2p/kW⋅h. Other estimates also give a figure of 0.2p/kW⋅h. However, Bernard Quigg notes: "According to the 06/07 annual accounts for NGC UK transmission, NGC carried 350TW⋅h for an income of £2012m in 2007, i. e. NGC receives 0.66p per kW hour. With two years inflation to 2008/9, say 0.71p per kW⋅h.", but this also includes generators' connection fees. In order to be allowed to supply electricity to

SECTION 20

#1732883532742

1474-476: Is populated from information sent from the supplier regarding the metering system. Only non-domestic users (with two valid MPANs that are not Profile Class 1 or 2) can register to access this service. The final digit in the MPAN is the check digit, and validates the previous 12 (the core) using a modulus 11 test. The check digit is calculated thus: In Matlab: In Pascal / Delphi: In Ruby: In Visual Basic: In VisualBasic.Net 2010: Or VB.Net 2010, avoiding

1541-649: Is so small. Following the closure of the feed-in tariffs , in January 2020 Ofgem introduced the Smart Export Guarantee (SEG) arrangements, where an export MPAN is allocated to allow a supplier to pay a customer for export of low-carbon energy. Export capacity over 30 kW is required to be half-hourly metered. As part of the Marketwide Half Hourly Arrangements (MHHS), all export consumption will be required to be registered and settled on

1608-517: Is sometimes described as being a 'secret' location. As of 2015 the system is under consistent cyber attack . Although the transmission network in Scotland is owned by separate companies – SP Transmission plc (part of ScottishPower ) in the south, and Scottish Hydro Electric Transmission plc (part of Scottish and Southern Electricity Networks ) in the north – overall control rests with National Grid Electricity System Operator. The costs of operating

1675-538: Is the case with 'net zero'). In 2020 about 40% of the grid's energy came from burning natural gas, and it is not expected that anywhere close to sufficient green power will be available to run the grid on zero carbon in 2025, except perhaps on the very windiest days. Analysts such as Hartree Solutions considered in 2020 that getting to 'net zero' by 2050 would be challenging, even more so to reach 'net zero' by 2033. There has, however, been sustained progress towards carbon neutrality , with carbon intensity falling by 53% in

1742-424: Is the check digit. The first two digits of a full MPAN reflect its profile class. Profile class 00 supplies are half-hourly (HH) metered, i.e. they record electricity consumption for every half hour of every day, and supplies of the other profile classes are non-half-hourly (NHH) metered. A NHH supply must be upgraded to HH where: Any Metering System where the average of the maximum monthly electrical demands in

1809-459: Is the customer's responsibility to maintain an accurate and up-to-date inventory of unmetered supplies, and to inform the UMSO (UnMetered Supplies Operator) of all changes to the connected equipment within one month of the change. Larger local authorities generally have unmetered supplies with a demand over 100kW and are required to trade their unmetered energy on a half-hourly basis. To do so, they employ

1876-420: Is the final 13 digits of the MPAN, and uniquely identifies an exit point. It consists of a two-digit Distributor ID, followed by an eight-digit unique identifier, then by two digits and a single check digit. Great Britain is divided into fourteen distribution areas. For each area a single company, the distribution network operator , has a licence to distribute electricity. They effectively carry electricity from

1943-698: The Isle of Man , and DC connectors to Northern Ireland, the Shetland Islands , the Republic of Ireland, France, Belgium, the Netherlands, Norway, and Denmark. Since the privatisation of the Central Electricity Generating Board in 1990, the National Grid in England and Wales is owned by National Grid plc . In Scotland the grid is owned by ScottishPower Transmission in the south, and by SSE in

2010-490: The National Grid to the exit points (each having a unique MPAN and a possibility of several meters) where the customers are. The owner of the distribution network charges electricity suppliers for carrying the electricity in their network. Their DNO licensed regions are the same geographic areas as the former nationalised electricity boards . In addition to the distribution network operators noted above who are licensed for

2077-704: The Supergrid . In the 2010 issue of the code that governs the National Grid, the Grid Code , the Supergrid is defined as those parts of the British electricity transmission system that are connected at voltages in excess of 200 kV. The 2.2 GW undersea Western HVDC Link from Scotland to North Wales was built in 2013–2018. This was the first major non- alternating current grid link within Great Britain, although interconnectors to foreign grids already used HVDC . In 2021

MPAN - Misplaced Pages Continue

2144-520: The Western Isles which have limited connectivity ), Wales , and the Isle of Man . The following figures are taken from the 2005 Seven Year Statement. Total generating capacity is supplied roughly equally by renewable , gas fired, nuclear , coal fired power stations . Annual energy transmitted in the UK grid is around 300–360 TWh (1.1–1.3 EJ), with an average load factor of 72% (i.e. 3.6×10 /(8,760 × 57×10 ). The National Grid has

2211-494: The MPAN can be in one of four states: disconnected, de-energised, live, and new. These terms are by no means standardised. For example, a disconnected supply might be referred to as a 'dead' supply. The vast majority of MPANs are import MPANs, where energy is being consumed. However, if a supply exports to the distribution network, then an export MPAN is issued. If a supply both imports and exports, then both an import MPAN and export MPAN are issued. Formerly, export MPANs required

2278-512: The National Grid System are recouped by National Grid Electricity System Operator (NGESO) through levying of Transmission Network Use of System (TNUoS) charges on the users of the system. The costs are split between the generators and the users of electricity. Tariffs are set annually by NGESO, and the country is divided into zones, each with a different tariff for generation and consumption. In general, tariffs are higher for generators in

2345-401: The National Grid are low, there are significant further losses in onward electricity distribution to the consumer, causing a total distribution loss of about 7.7%. Losses differ significantly for customers connected at different voltages; connected at high voltage the total losses are about 2.6%, at medium voltage 6.4% and at low voltage 12.2%. Generated power entering the grid is metered at

2412-531: The National Grid: the users pay less if they can manage their usage so as to be less peaky. For each year's calculation, historic system demand metrics are analysed to determine three half-hour periods of high average demand; the three periods are known as triads. The periods are (a) the period of peak system demand, and (b) two other periods of highest demand which are separated from peak system demand and from each other by at least ten days. For power stations,

2479-530: The Republic of Ireland (500 MW HVDC East–West Interconnector ), and Denmark (1.4 GW Viking Link ). A further 500 MW link with the Republic of Ireland ( Greenlink ) is scheduled for 2024. Further potential schemes include links with Germany ( NeuConnect , 1.4 GW); Iceland ( Icelink , around 1 GW) and Morocco (3.6 GW from new battery-backed solar generation). The UK grid has access to large pumped storage systems, notably Dinorwig Power Station which can provide 1.7 GW for 5–6 hours, and

2546-557: The UK's electricity interconnection level (off-island transmission capacity relative to production capacity) was 6%. As of 2024 , the total capacity of these connectors is over 9 GW. They include direct-current cables to northern France (2 GW HVDC Cross-Channel , 1 GW HVDC IFA-2 , 1 GW ElecLink via the Channel Tunnel ); Belgium (1 GW HVDC Nemo Link ); the Netherlands (1 GW HVDC BritNed ); Norway (1.4 GW HDVC North Sea Link ); Northern Ireland (500 MW HVDC Moyle Interconnector );

2613-553: The United Kingdom was by Charles Merz , of the Merz & McLellan consulting partnership, at his Neptune Bank Power Station near Newcastle upon Tyne . This opened in 1901, and by 1912 had developed into the largest integrated power system in Europe. The rest of the country, however, continued to use a patchwork of small supply networks. In 1925, the British government asked Lord Weir ,

2680-603: The anticipated transfer in 1970 of some 6,000 MW from the Midlands to the home counties . Continued reinforcement and extension of the 275 kV systems was examined as a possible solution. However, in addition to the technical problem of high fault levels, many more lines would have been required to obtain the estimated transfers at 275 kV. As this was not consistent with the Central Electricity Generating Board's policy of preservation of amenities,

2747-519: The chargeable demand is only the net site demand (per CUSC rule 14.17.10), so when the site is net exporting (i.e. total metered generation at that site exceeds total separately metered station demand), that separately metered station demand shall not be liable for demand TNUoS charges in relation to the station demand at triad. Triad dates in recent years were: This is the main source of income which National Grid uses to cover its costs for high-voltage long-distance transmission (lower voltage distribution

MPAN - Misplaced Pages Continue

2814-592: The customer load from the Supergrid to avoid blacking out the entire grid. Reserve services are a group of services each acting within different response times: These reserves are sized according to three factors: The English and Welsh parts of the National Grid are controlled from the National Grid Control Centre which is located in St Catherine's Lodge, Sindlesham , Wokingham in Berkshire. It

2881-535: The customer's appointed electricity supplier for billing, with an electronic copy of the EAC being sent to the appointed data collector. The DNO make a Distribution Use of System charge on the electricity supplier for the delivery of the electricity to the customer's unmetered equipment. Each non-half-hourly supply has a four digit code called the Standard Settlement Configuration (SSC), which specifies

2948-411: The data is downloaded daily the authority will see their energy invoices change throughout the year to represent the changes in the seasonal daily lighting levels. If, however, the unmetered supplies are being traded as non half-hourly the UMSO undertakes the responsibility to calculate an EAC (Estimated Annual Consumption). This is done using a simple formula which takes into account the circuit watts of

3015-422: The distribution network via an unmetered connection, its consumption should typically not exceed 500 watts and it should operate in a predictable manner, with no provision for it to be manually turned on/off at the end user's request. Generally the equipment would either be in operation and taking a supply of electricity 24 hours a day, or be controlled by a photocell, as is often the case for street lights. It

3082-538: The equipment and the annual hours of operation. For example, a piece of equipment that is in use 24 hours per day will have annual hours of 8766. For, say, a CCTV camera rated at 24 circuit watts the EAC would be 210.384kWh, calculated as circuit watts × annual hours divided by 1000. As a result of Ofgem's decision to progress with Marketwide Half Hourly Settlement (MHHS) all new unmetered supplies from April 2024 will be half hourly and existing non half-hourly unmetered supplies will move to half hourly trading during 2024. If

3149-409: The equipment is street lighting the same process is used for non half-hourly; however, the annual hours will change as each photocell is assigned a set number of annual hours which indicate how and when the lights turn on and off. These annual hours have been set by Elexon and are not locally agreed with the UMSO by the customer. Once an EAC calculation has taken place, an EAC Certificate is provided to

3216-412: The final 13 digits and is the unique identifier. The top line data gives information about the characteristics of the supply and is the responsibility of the supplier. The full MPAN is required to be depicted on electricity bills (the boxes on the top and bottom line are generally unaligned). The core data is on the second line, the supplementary data on the first. Only the last digit on the bottom row

3283-466: The five years to 2020. The phase out of coal is progressing rapidly with only 1.6% of the UK's electricity coming from coal in 2020, compared with about 25% in 2015. 2020 saw the UK go more than two months without needing to burn any coal for electricity, the longest period since the Industrial Revolution . Figures are again from the 2005 Seven Year Statement. Although overall losses in

3350-401: The high-voltage side of the generator transformer. Any power losses in the generator transformer are therefore accounted to the generating company, not to the grid system. The power loss in the generator transformer does not contribute to the grid losses. In 2009–10 there was an average power flow of about 11 GW from the north of the UK, particularly from Scotland and northern England, to

3417-490: The majority of Great Britain and some of the surrounding islands. It does not cover Northern Ireland , which is part of the Irish single electricity market . The National Grid is a wide area synchronous grid operating at a nominal 50 hertz. Most of the physical HV parts of the grid consists of 400 kV lines as well as some 275 kV lines that collectively form a supergrid . It has several undersea interconnectors : an AC connector to

SECTION 50

#1732883532742

3484-460: The night-time engineers on 29 October 1937, by 1938 the grid was operating as a national system. The growth by then in the number of electricity users was the fastest in the world, rising from three quarters of a million in 1920 to nine million in 1938. The grid proved its worth during the Blitz , when South Wales provided power to replace lost output from Battersea and Fulham power stations. The grid

3551-429: The north and consumers in the south since there is generally a north–south flow of electricity. 'Triad demand' is a metric of demand which reports retrospectively three numbers about peak demand between November and February (inclusive) each winter. In order to encourage usage of the National Grid to be less 'peaky', the triad is used as the basis for extra charges paid by the users (the licensed electricity suppliers) to

3618-480: The north. Infrastructure connecting offshore wind farms to the grid is owned by offshore transmission owners . National Grid plc is the transmission system operator for the whole GB grid. At the end of the 19th century, Nikola Tesla established the principles of three-phase high-voltage electric power distribution while he was working for Westinghouse in the United States. The first use of this system in

3685-404: The number of registers a meter has, and the times that each register is recording electricity usage. The times that a register is recording is specified with a five digit code Time Pattern Regime (TPR). So for example a supply with SSC 0943 has two registers with TPRs 00404 and 00405. The 00404 TPR register records from 01:00 to 02:30 and 08:00 to 23:30, and the 00405 register records for the rest of

3752-405: The same term [REDACTED] This disambiguation page lists articles associated with the title MPAN . If an internal link led you here, you may wish to change the link to point directly to the intended article. Retrieved from " https://en.wikipedia.org/w/index.php?title=MPAN&oldid=1136848489 " Category : Disambiguation pages Hidden categories: Short description

3819-464: The smaller Cruachan and Ffestiniog . There are also some grid batteries . As of May 2021, 1.3 GW of battery storage was operating in the United Kingdom, with 16 GW of projects in the pipeline potentially deployable over the next few years. A 100 MW power Chinese-financed plant at Minety , Wiltshire was reported to be the largest in Europe when it opened in July 2021; when a 50 MW extension

3886-518: The south coast has about 12% greater effectiveness due to reduced transmission system power losses compared to new generating capacity in north England, and about 20% greater effectiveness than in northern Scotland. There is a 40 MW AC cable to the Isle of Man, the Isle of Man to England Interconnector and a 260km 600MW HVDC cable to the Shetland Islands . The UK grid is connected to adjacent European electrical grids by submarine power cables . In 2014,

3953-497: The south of the UK across the grid. This flow was anticipated to grow to about 12 GW by 2014. Completion of the Western HVDC Link in 2018 added capacity for a flow of 2.2 GW between Western Scotland and North Wales. Because of the power loss associated with this north to south flow, the effectiveness and efficiency of new generation capacity is significantly affected by its location. For example, new generating capacity on

4020-530: The system's AC frequency within ±1% of 50  Hz , except in exceptional circumstances. These are used on a second by second basis to either lower the demand or to provide extra generation. In an emergency where the discrepancy between supply and demand is too great and the frequency drops too far (between 48.8 Hz down to 47.8 Hz) then the Low Frequency Demand Disconnection (LFDD) automatic cutouts progressively trigger and remove up to 60% of

4087-416: The three months of highest demand, either in: exceeds 100kW. HH data is recorded by the meter and collected by an onsite download, or by remote communication methods such as GSM , SMS , GPRS or telephone line. Domestic NHH import MPANs always have a profile class of 01 or 02. Domestic NHH export MPANs are allocated a profile class of 08. The MTC is a 3 digit code that reflects the various registers

SECTION 60

#1732883532742

4154-569: The time. Each DNO operates a Meter Point Administration System (MPAS) which holds the following information for each MPAN: MPRS is the name of the software package that implements the MPAS system for all DNOs. Since MPRS is used by most DNOs it is often used interchangeably with the term MPAS. ECOES (formally the Electricity Central Online Enquiry Service) is now the Electricity Enquiry Service (EES)

4221-403: The transmission system, generators must be licensed (by BEIS) and enter into a connection agreement with NGET which also grants Transmission Entry Capacity (TEC). Generators contribute to the costs of running the system by paying for TEC, at the generation TNUoS tariffs set by NGET. This is charged on a maximum-capacity basis. In other words, a generator with 100 MW of TEC who only generated at

4288-491: The use of VB6 Compatibility Library : In C#: As a formula in Excel 365: In Python: In PL/SQL: In JavaScript: In PHP: National Grid (UK) The National Grid is the high-voltage electric power transmission network serving Great Britain , connecting power stations and major substations , and ensuring that electricity generated anywhere on the grid can be used to satisfy demand elsewhere. The network serves

4355-477: Was already exceeded by 1960. This rapid growth led the Central Electricity Generating Board (created in 1958) to carry out a study in 1960 of future transmission needs. Considered in the study, together with the increased demand, was the effect on the transmission system of the rapid advances in generator design resulting in projected power stations of 2,000–3,000 MW installed capacity. These new stations were mostly to be sited where advantage could be taken of

4422-522: Was created with 6,400 kilometres (4,000 miles) of cables – mostly overhead – linking the 122 most efficient power stations. The first "grid tower" was erected near Edinburgh on 14 July 1928, and work was completed in September 1933, ahead of schedule and on budget. It began operating in 1933 as a series of regional grids with auxiliary interconnections for emergency use. Following the unauthorised but successful short term parallelling of all regional grids by

4489-602: Was nationalised by the Electricity Act 1947 , which also created the British Electricity Authority . In 1949, the British Electricity Authority decided to upgrade the grid by adding 275 kV links. At its inception in 1950, the 275 kV Transmission System was designed to form part of a national supply system with an anticipated total demand of 30,000 MW by 1970. The predicted demand

#741258