Longtan Dam ( simplified Chinese : 龙滩大坝 ; traditional Chinese : 龍灘大壩 ; pinyin : Lóngtān Dàbà ) is a large roller-compacted concrete (RCC) gravity dam on the Hongshui River in Tian'e County of the Guangxi Zhuang Autonomous Region , China , a tributary of the Xi River and the Pearl River . The dam is 216.2 metres (709.3 ft) high and 849 m (2,785 ft) long; it is the tallest of its type in the world. The dam is intended for hydroelectric power production, flood control and navigation . The dam contains seven surface spillways, two bottom outlets and an underground power station . The Longtan ship lift , part of the dam complex, will be the tallest ship lift system in the world.
98-423: The dam was planned in the 1950s, but preliminary construction (roads, bridges, river diversion) did not begin until 1940s. Formal construction began on the project July 1, 2001, and the river was diverted by November 2003. A total of 20,000,000 m (706,293,334 cu ft) of material were excavated from the dam site. Impounding of the 27,270,000,000 m (22,108,149 acre⋅ft) reservoir began in 2006, and
196-737: A greenhouse gas . According to the World Commission on Dams report, where the reservoir is large compared to the generating capacity (less than 100 watts per square metre of surface area) and no clearing of the forests in the area was undertaken prior to impoundment of the reservoir, greenhouse gas emissions from the reservoir may be higher than those of a conventional oil-fired thermal generation plant. In boreal reservoirs of Canada and Northern Europe, however, greenhouse gas emissions are typically only 2% to 8% of any kind of conventional fossil-fuel thermal generation. A new class of underwater logging operation that targets drowned forests can mitigate
294-463: A low-head hydro power plant with hydrostatic head of few meters to few tens of meters can be classified either as an SHP or an LHP. The other distinction between SHP and LHP is the degree of the water flow regulation: a typical SHP primarily uses the natural water discharge with very little regulation in comparison to an LHP. Therefore, the term SHP is frequently used as a synonym for the run-of-the-river power plant . The largest power producers in
392-495: A 10-inch (250 mm) piston and a stroke of 15 feet (4.6 m), which enabled pressures of 600 pounds per square inch (41 bar) to be achieved. Compared to the 80 psi (5.5 bar) of the Newcastle scheme, this increased pressure significantly reduced the volumes of water used. Cranes were not the only application, with hydraulic operation of the dock gates at Swansea reducing the operating time from 15 to two minutes, and
490-513: A demonstration of the crane's versatility, given by the crane driver John Thorburn, known locally as "Hydraulic Jack". While the Newcastle system ran on water from the public water supply, the crane installed by Armstrong at Burntisland was not located where such an option was possible, and so he built a 180-foot (55 m) tower, with a water tank at the top, which was filled by a 6 hp (4.5 kW) steam engine. At Elswick in Glasgow, charges by
588-421: A flood and fail. Changes in the amount of river flow will correlate with the amount of energy produced by a dam. Lower river flows will reduce the amount of live storage in a reservoir therefore reducing the amount of water that can be used for hydroelectricity. The result of diminished river flow can be power shortages in areas that depend heavily on hydroelectric power. The risk of flow shortage may increase as
686-494: A hydroelectric complex is constructed, it produces no direct waste, and almost always emits considerably less greenhouse gas than fossil fuel -powered energy plants. However, when constructed in lowland rainforest areas, where part of the forest is inundated, substantial amounts of greenhouse gases may be emitted. Construction of a hydroelectric complex can have significant environmental impact, principally in loss of arable land and population displacement. They also disrupt
784-809: A large natural height difference between two waterways, such as a waterfall or mountain lake. A tunnel is constructed to take water from the high reservoir to the generating hall built in a cavern near the lowest point of the water tunnel and a horizontal tailrace taking water away to the lower outlet waterway. A simple formula for approximating electric power production at a hydroelectric station is: P = − η ( m ˙ g Δ h ) = − η ( ( ρ V ˙ ) g Δ h ) {\displaystyle P=-\eta \ ({\dot {m}}g\ \Delta h)=-\eta \ ((\rho {\dot {V}})\ g\ \Delta h)} where Efficiency
882-451: A larger amount of methane than those in temperate areas. Like other non-fossil fuel sources, hydropower also has no emissions of sulfur dioxide, nitrogen oxides, or other particulates. Reservoirs created by hydroelectric schemes often provide facilities for water sports , and become tourist attractions themselves. In some countries, aquaculture in reservoirs is common. Multi-use dams installed for irrigation support agriculture with
980-586: A positive risk adjusted return, unless appropriate risk management measures are put in place. While many hydroelectric projects supply public electricity networks, some are created to serve specific industrial enterprises. Dedicated hydroelectric projects are often built to provide the substantial amounts of electricity needed for aluminium electrolytic plants, for example. The Grand Coulee Dam switched to support Alcoa aluminium in Bellingham, Washington , United States for American World War II airplanes before it
1078-446: A public system in 1879, using a 300 hp (220 kW) steam engine installed at the Pont de la Machine to pump water from Lake Geneva, which provided drinking water and a pressurized water supply for the city. The water power was used by about a hundred small workshops having Schmid-type water engines installed. The power of the engines was between 1 and 4 hp (0.75 and 2.98 kW) and
SECTION 10
#17330844674991176-545: A relatively constant water supply. Large hydro dams can control floods, which would otherwise affect people living downstream of the project. Managing dams which are also used for other purposes, such as irrigation , is complicated. In 2021 the IEA called for "robust sustainability standards for all hydropower development with streamlined rules and regulations". Large reservoirs associated with traditional hydroelectric power stations result in submersion of extensive areas upstream of
1274-526: A result of climate change . One study from the Colorado River in the United States suggest that modest climate changes, such as an increase in temperature in 2 degree Celsius resulting in a 10% decline in precipitation, might reduce river run-off by up to 40%. Brazil in particular is vulnerable due to its heavy reliance on hydroelectricity, as increasing temperatures, lower water flow and alterations in
1372-448: A small TV/radio). Even smaller turbines of 200–300 W may power a few homes in a developing country with a drop of only 1 m (3 ft). A Pico-hydro setup is typically run-of-the-river , meaning that dams are not used, but rather pipes divert some of the flow, drop this down a gradient, and through the turbine before returning it to the stream. An underground power station is generally used at large facilities and makes use of
1470-455: A source of low-cost renewable energy. Alternatively, small hydro projects may be built in isolated areas that would be uneconomic to serve from a grid, or in areas where there is no national electrical distribution network. Since small hydro projects usually have minimal reservoirs and civil construction work, they are seen as having a relatively low environmental impact compared to large hydro. This decreased environmental impact depends strongly on
1568-414: A start-up time of the order of a few minutes. Although battery power is quicker its capacity is tiny compared to hydro. It takes less than 10 minutes to bring most hydro units from cold start-up to full load; this is quicker than nuclear and almost all fossil fuel power. Power generation can also be decreased quickly when there is a surplus power generation. Hence the limited capacity of hydropower units
1666-418: A stilling pond, 19 aqueducts and six tunnels. The spare horsepower generated water motors, water engines and turbines in the town of Oamaru for decades and operated for 103 years. Much of the race and its components can still be seen today. Bristol Harbour still has a working system, the pumping machinery of which was supplied by Fullerton, Hodgart and Barclay of Paisley , Scotland in 1907. The engine house
1764-538: A stroke of 20 feet (6.1 m) and each loaded with a 93-tonne weight. The gas engines were started by a small hydraulic engine, which used the hydraulic energy stored in the accumulators, and all equipment was supplied by Ellington's company. Very few documents describing the details of the system are known to exist. The final two public systems in Britain were in Manchester , commissioned in 1894, and Glasgow , commissioned
1862-581: A total of 1,500 terawatt-hours (TWh) of electrical energy in one full cycle" which was "about 170 times more energy than the global fleet of pumped storage hydropower plants". Battery storage capacity is not expected to overtake pumped storage during the 2020s. When used as peak power to meet demand, hydroelectricity has a higher value than baseload power and a much higher value compared to intermittent energy sources such as wind and solar. Hydroelectric stations have long economic lives, with some plants still in service after 50–100 years. Operating labor cost
1960-420: A total of 18 turbines had been installed, with a combined rating of 3.3MW. The distribution network used three different pressure levels. The drinking water supply used the lowest pressure, while the intermediate and the high pressure mains served as hydraulic power networks. The intermediate pressure mains operated at 6.5 bars (94 psi) and by 1896 some 51 miles (82 km) of pipework had been installed. It
2058-432: A variety of other useful purposes, to which the same has never before been so applied". Major components of the system were a ring main, into which a number of pumping stations would pump the water, with pressure being regulated by several air vessels or loaded pistons. Pressure relief valves would protect the system, which he believed could deliver water at a pressure of "a great plurality of atmospheres", and in concept, this
SECTION 20
#17330844674992156-482: A year's worth of rain fell within 24 hours (see 1975 Banqiao Dam failure ). The resulting flood resulted in the deaths of 26,000 people, and another 145,000 from epidemics. Millions were left homeless. The creation of a dam in a geologically inappropriate location may cause disasters such as 1963 disaster at Vajont Dam in Italy, where almost 2,000 people died. Hydraulic power network A hydraulic power network
2254-448: Is hydroelectric power on a scale serving a small community or industrial plant. The definition of a small hydro project varies but a generating capacity of up to 10 megawatts (MW) is generally accepted as the upper limit. This may be stretched to 25 MW and 30 MW in Canada and the United States. Small hydro stations may be connected to conventional electrical distribution networks as
2352-426: Is a grade II* listed building, constructed in 1887, fully commissioned by 1888, with a tower at one end to house the hydraulic accumulator. A second accumulator was fitted outside the building (dated 1954) which enables the operation of the system to be more easily visualised. A number of artefacts, including the buildings used as pumping stations, have survived the demise of public hydraulic power networks. In Hull,
2450-415: Is a system of interconnected pipes carrying pressurized liquid used to transmit mechanical power from a power source, like a pump , to hydraulic equipment like lifts or motors . The system is analogous to an electrical grid transmitting power from a generating station to end-users. Only a few hydraulic power transmission networks are still in use; modern hydraulic equipment has a pump built into
2548-627: Is also usually low, as plants are automated and have few personnel on site during normal operation. Where a dam serves multiple purposes, a hydroelectric station may be added with relatively low construction cost, providing a useful revenue stream to offset the costs of dam operation. It has been calculated that the sale of electricity from the Three Gorges Dam will cover the construction costs after 5 to 8 years of full generation. However, some data shows that in most countries large hydropower dams will be too costly and take too long to build to deliver
2646-466: Is highest in the winter when solar energy is at a minimum. Pico hydro is hydroelectric power generation of under 5 kW . It is useful in small, remote communities that require only a small amount of electricity. For example, the 1.1 kW Intermediate Technology Development Group Pico Hydro Project in Kenya supplies 57 homes with very small electric loads (e.g., a couple of lights and a phone charger, or
2744-445: Is initially produced during construction of the project, and some methane is given off annually by reservoirs, hydro has one of the lowest lifecycle greenhouse gas emissions for electricity generation. The low greenhouse gas impact of hydroelectricity is found especially in temperate climates . Greater greenhouse gas emission impacts are found in the tropical regions because the reservoirs of power stations in tropical regions produce
2842-471: Is more than all other renewable sources combined and also more than nuclear power . Hydropower can provide large amounts of low-carbon electricity on demand, making it a key element for creating secure and clean electricity supply systems. A hydroelectric power station that has a dam and reservoir is a flexible source, since the amount of electricity produced can be increased or decreased in seconds or minutes in response to varying electricity demand. Once
2940-462: Is not an energy source, and appears as a negative number in listings. Run-of-the-river hydroelectric stations are those with small or no reservoir capacity, so that only the water coming from upstream is available for generation at that moment, and any oversupply must pass unused. A constant supply of water from a lake or existing reservoir upstream is a significant advantage in choosing sites for run-of-the-river. A tidal power station makes use of
3038-452: Is not generally used to produce base power except for vacating the flood pool or meeting downstream needs. Instead, it can serve as backup for non-hydro generators. The major advantage of conventional hydroelectric dams with reservoirs is their ability to store water at low cost for dispatch later as high value clean electricity. In 2021, the IEA estimated that the "reservoirs of all existing conventional hydropower plants combined can store
Longtan Dam - Misplaced Pages Continue
3136-410: Is often higher (that is, closer to 1) with larger and more modern turbines. Annual electric energy production depends on the available water supply. In some installations, the water flow rate can vary by a factor of 10:1 over the course of a year. Hydropower is a flexible source of electricity since stations can be ramped up and down very quickly to adapt to changing energy demands. Hydro turbines have
3234-773: The Albert Dock (1869), and Alexandra Dock (1885) installed hydraulic generating stations and accumulators. The best-known public hydraulic network was the citywide network of the London Hydraulic Power Company . This was formed in 1882, as the General Hydraulic Power Company, with Ellington as the consulting engineer. By the following year another enterprise, the Wharves and Warehouses Steam Power and Hydraulic Pressure Company, had begun to operate, with 7 miles (11 km) of pressure mains on both sides of
3332-657: The Bonneville Dam in 1937 and being recognized by the Flood Control Act of 1936 as the premier federal flood control agency. Hydroelectric power stations continued to become larger throughout the 20th century. Hydropower was referred to as "white coal". Hoover Dam 's initial 1,345 MW power station was the world's largest hydroelectric power station in 1936; it was eclipsed by the 6,809 MW Grand Coulee Dam in 1942. The Itaipu Dam opened in 1984 in South America as
3430-778: The International Exhibition of Hydropower and Tourism , with over one million visitors 1925. By 1920, when 40% of the power produced in the United States was hydroelectric, the Federal Power Act was enacted into law. The Act created the Federal Power Commission to regulate hydroelectric power stations on federal land and water. As the power stations became larger, their associated dams developed additional purposes, including flood control , irrigation and navigation . Federal funding became necessary for large-scale development, and federally owned corporations, such as
3528-535: The Museum of Science and Industry , where it has been restored to working order and forms part of a larger display about hydraulic power. The pumps were made by the Manchester firm of Galloways. Geneva still has its Jet d'Eau fountain, but since 1951 it has been powered by a partially submerged pumping station, which uses water from the lake rather than the city water supply. Two Sulzer pumps, named Jura and Salève, create
3626-564: The River Thames . These supplied cranes, dock gates, and other heavy machinery. Under the terms of an Act of Parliament obtained in 1884, the two companies amalgamated to become the London Hydraulic Power Company. Initially supplying 17.75 million gallons (80.7 megalitres) of high-pressure water each day, this had risen to 1,650 million gallons (7,500 megalitres) by 1927, when the company was powering around 8,000 machines from
3724-585: The Spencer Street power station , which thus supplied both electric power and hydraulic power to the city. The hydraulic system continued to operate under municipal ownership until December 1967. In January 1891, a system in Sydney came on-line, having been authorised by act of Parliament in 1888. George Swinburne was again the engineer, and the system was supplying power to around 200 machines by 1894, which included 149 lifts and 20 dock cranes. The operating company
3822-605: The Tennessee Valley Authority (1933) and the Bonneville Power Administration (1937) were created. Additionally, the Bureau of Reclamation which had begun a series of western US irrigation projects in the early 20th century, was now constructing large hydroelectric projects such as the 1928 Hoover Dam . The United States Army Corps of Engineers was also involved in hydroelectric development, completing
3920-569: The Vulcan Street Plant , began operating September 30, 1882, in Appleton, Wisconsin , with an output of about 12.5 kilowatts. By 1886 there were 45 hydroelectric power stations in the United States and Canada; and by 1889 there were 200 in the United States alone. At the beginning of the 20th century, many small hydroelectric power stations were being constructed by commercial companies in mountains near metropolitan areas. Grenoble , France held
4018-506: The potential energy of dammed water driving a water turbine and generator . The power extracted from the water depends on the volume and on the difference in height between the source and the water's outflow. This height difference is called the head . A large pipe (the " penstock ") delivers water from the reservoir to the turbine. This method produces electricity to supply high peak demands by moving water between reservoirs at different elevations. At times of low electrical demand,
Longtan Dam - Misplaced Pages Continue
4116-635: The station at Wapping is virtually complete, retaining all of its equipment, which is still in working order. The building is grade II* listed because of its completeness. In Manchester, the Water Street pumping station, built in Baroque style between 1907 and 1909, was used as workshops for the City College, but has formed part of the People's History Museum since 1994. One of the pumping sets has been moved to
4214-462: The 1840s, using low-pressure water, but a breakthrough occurred in 1850 with the introduction of the hydraulic accumulator , which allowed much higher pressures to be used. The first public network, supplying many companies, was constructed in Kingston upon Hull , England. The Hull Hydraulic Power Company began operation in 1877, with Edward B. Ellington as its engineer. Ellington was involved in most of
4312-687: The 1940s, when the systematic bombing of the city during the Second World War led to the destruction of much of the infrastructure, and the company was wound up in 1947, when Mr F J Haswell, who had been the manager and engineer since 1904, retired. The man responsible for the Hull system was Edward B. Ellington , who had risen to become the managing director of the Hydraulic Engineering Company, based in Chester, since first joining it in 1869. At
4410-508: The British networks, and some further afield. Public networks were constructed in Britain at London, Liverpool , Birmingham , Manchester and Glasgow . There were similar networks in Antwerp , Melbourne , Sydney , Buenos Aires and Geneva . All of the public networks had ceased to operate by the mid-1970s, but Bristol Harbour still has an operational system, with an accumulator situated outside
4508-488: The Corporation Water Department for the water used persuaded the owners that the use of a steam-powered crane would be cheaper. Bramah's concept of "loaded pistons" was introduced in 1850, when the first hydraulic accumulator was installed as part of a scheme for cranes for the Manchester, Sheffield and Lincolnshire Railway . A scheme for cranes at Paddington the following year specified an accumulator with
4606-463: The IEA released a main-case forecast of 141 GW generated by hydropower over 2022–2027, which is slightly lower than deployment achieved from 2017–2022. Because environmental permitting and construction times are long, they estimate hydropower potential will remain limited, with only an additional 40 GW deemed possible in the accelerated case. In 2021 the IEA said that major modernisation refurbishments are required. Most hydroelectric power comes from
4704-510: The Machell Street pumping station has been reused as a workshop. The building still supports the sectional cast-iron roof tank used to allow the silt-laden water of the River Hull to settle, and is marked by a Blue plaque , to commemorate its importance. In London, Bermondsey pumping station, built in 1902, is in use as an engineering works, but retains its chimney and accumulator tower, while
4802-455: The Second World War, due to the destruction of customers' machinery and premises. Following the hostilities, large areas of London were reconstructed, and the re-routing of pressure mains was much more difficult than the provision of an electric supply, so that by 1954 the number of machines had fallen to 4,286. The company was wound up in 1977. A system began operating in Liverpool in 1888. It
4900-576: The Victorian Parliament passed in December 1887, and construction of the system began, with Coates & Co. acting as consulting engineers, and George Swinburne working as engineering manager. The steam pumping plant was supplied by Abbot & Co. from England. Expansion was rapid, with around 70 machines, mainly hydraulic lifts, connected to the system by the end of 1889, and a third steam engine had to be installed in mid-1890, which more than doubled
4998-464: The ability to transport particles heavier than itself downstream. This has a negative effect on dams and subsequently their power stations, particularly those on rivers or within catchment areas with high siltation. Siltation can fill a reservoir and reduce its capacity to control floods along with causing additional horizontal pressure on the upstream portion of the dam. Eventually, some reservoirs can become full of sediment and useless or over-top during
SECTION 50
#17330844674995096-595: The balance between stream flow and power production. Micro hydro means hydroelectric power installations that typically produce up to 100 kW of power. These installations can provide power to an isolated home or small community, or are sometimes connected to electric power networks. There are many of these installations around the world, particularly in developing nations as they can provide an economical source of energy without purchase of fuel. Micro hydro systems complement photovoltaic solar energy systems because in many areas water flow, and thus available hydro power,
5194-541: The capacity of the system. A fourth pumping engine was added in 1891, by which time there were 100 customers connected to the mains. The mains were a mixture of 4-inch (100 mm) and 6-inch (150 mm) pipes. The water was extracted from the Yarra River until 1893, after which it was drawn from the Public Works Department's supply. There were some 16 miles (26 km) of mains by 1897. A second pumping station
5292-471: The cranes on the quay should be converted to hydraulic power. He was required to carry out the work at his own expense, but would be rewarded if the conversion was a success. It was, and he set up the Newcastle Cranage Company, which received an order for the conversion of the other four cranes. Further work followed, with the engineer from Liverpool Docks visiting Newcastle and being impressed by
5390-404: The daily rise and fall of ocean water due to tides; such sources are highly predictable, and if conditions permit construction of reservoirs, can also be dispatchable to generate power during high demand periods. Less common types of hydro schemes use water's kinetic energy or undammed sources such as undershot water wheels . Tidal power is viable in a relatively small number of locations around
5488-496: The dam and ship lift will turn the Hongshui into a "golden waterway" for reaching landlocked Guizhou and Guangxi provinces. http://www.fao.org/nr/water/aquastat/countries_regions/Profile_segments/CHN-WR_eng.stm Hydroelectric Hydroelectricity , or hydroelectric power , is electricity generated from hydropower (water power). Hydropower supplies 15% of the world's electricity , almost 4,210 TWh in 2023, which
5586-526: The dam's first of three operational hydroelectric generating units was testing May 2007. In 2009, the last generator became operational and the installed capacity increased to 6,426 MW , its annual generation is estimated at 18.7 TWh . A pair of tunnels diverted the river around the site of the dam, during construction. The dam will submerge over 300 shoals, which had rendered the upper Hongshui unnavigable. The Longtan ship lift will be able to lift vessels of up to 500 tonnes. Chinese officials assert
5684-505: The dams, sometimes destroying biologically rich and productive lowland and riverine valley forests, marshland and grasslands. Damming interrupts the flow of rivers and can harm local ecosystems, and building large dams and reservoirs often involves displacing people and wildlife. The loss of land is often exacerbated by habitat fragmentation of surrounding areas caused by the reservoir. Hydroelectric projects can be disruptive to surrounding aquatic ecosystems both upstream and downstream of
5782-464: The economic crisis of the 1930s, when the demand for pressurized water as an energy source declined. The last water engine was decommissioned in 1958. In order to avoid excessive pressure build-up in the hydraulic power network, a release valve was fitted beside the main hall of the powerhouse. A tall water fountain, the Jet d'Eau , was ejected by the device whenever it was activated. This typically happened at
5880-690: The effect of forest decay. Another disadvantage of hydroelectric dams is the need to relocate the people living where the reservoirs are planned. In 2000, the World Commission on Dams estimated that dams had physically displaced 40–80 million people worldwide. Because large conventional dammed-hydro facilities hold back large volumes of water, a failure due to poor construction, natural disasters or sabotage can be catastrophic to downriver settlements and infrastructure. During Typhoon Nina in 1975 Banqiao Dam in Southern China failed when more than
5978-429: The end of the day when the factories switched off their machines, making it hard to control the pressure in the system, and to adjust the supply of pressurized water to match the actual demand. The tall fountain was visible from a great distance and became a landmark in the city. When an engineering solution was found which made the fountain redundant, there was an outcry, and in 1891 it was moved to its current location in
SECTION 60
#17330844674996076-414: The entrance to Queens Dock. By 1895, pumps rated at 250 hp (190 kW) pumped some 500,000 imperial gallons (2,300 m ) of water into the system each week, and 58 machines were connected to it. The working pressure was 700 psi (48 bar), and the water was used to operate cranes, dock gates, and a variety of other machinery connected with ships and shipbuilding. The Hull system lasted until
6174-399: The excess generation capacity is used to pump water into the higher reservoir, thus providing demand side response . When the demand becomes greater, water is released back into the lower reservoir through a turbine. In 2021 pumped-storage schemes provided almost 85% of the world's 190 GW of grid energy storage and improve the daily capacity factor of the generation system. Pumped storage
6272-480: The following year, a Francis Turbine and generator made use of the surplus water to generate more electricity for the residents of the town. It was eventually decommissioned in 1946. The Oamaru Borough Water Race was designed by Donald McLeod (b.1835). It opened in 1880 after 3 years of construction. With water sourced from the Waitaki River , the race stretched nearly 50 km and comprised an intake structure,
6370-411: The following year. Both were equipped by Ellington's company, and used the higher pressure of 1,120 psi (77 bar). This was maintained by six sets of triple-expansion steam engines, rated at 200 hp (150 kW) each. Two accumulators with pistons of 18-inch (460 mm) diameter, a stroke of 23 feet (7.0 m), and loaded with 127 tonnes were installed. In Manchester, the hydraulic station
6468-519: The lake, where it operated solely as a tourist attraction, although the water to create it still came from the hydraulic network. Two systems were built in New Zealand . The Thames Water Race was built in 1876 to supply water to the Thames goldfields powering stamper batteries, pumps and mine-head lifting equipment. Later, electricity was supplied to the residents of Thames in 1914, and when goldmining ceased
6566-492: The largest amount for the region since 1990. Meanwhile, globally, hydropower generation increased by 70 TWh (up 2%) in 2022 and remains the largest renewable energy source, surpassing all other technologies combined. Hydropower has been used since ancient times to grind flour and perform other tasks. In the late 18th century hydraulic power provided the energy source needed for the start of the Industrial Revolution . In
6664-731: The largest, producing 14 GW , but was surpassed in 2008 by the Three Gorges Dam in China at 22.5 GW . Hydroelectricity would eventually supply some countries, including Norway , Democratic Republic of the Congo , Paraguay and Brazil , with over 85% of their electricity. In 2021 the International Energy Agency (IEA) said that more efforts are needed to help limit climate change . Some countries have highly developed their hydropower potential and have very little room for growth: Switzerland produces 88% of its potential and Mexico 80%. In 2022,
6762-609: The late 19th century, the electrical generator was developed and could now be coupled with hydraulics. The growing demand arising from the Industrial Revolution would drive development as well. In 1878, the world's first hydroelectric power scheme was developed at Cragside in Northumberland , England, by William Armstrong . It was used to power a single arc lamp in his art gallery. The old Schoelkopf Power Station No. 1 , US, near Niagara Falls , began to produce electricity in 1881. The first Edison hydroelectric power station,
6860-454: The machine. In the late 19th century, a hydraulic network might have been used in a factory, with a central steam engine or water turbine driving a pump and a system of high-pressure pipes transmitting power to various machines. The idea of a public hydraulic power network was suggested by Joseph Bramah in a patent obtained in 1812. William Armstrong began installing systems in England from
6958-561: The main pumphouse, enabling its operation to be easily visualised. Joseph Bramah , an inventor and locksmith living in London, registered a patent at the London Patent Office on 29 April 1812, which was principally about a provision of a public water supply network, but included a secondary concept for the provision of a high-pressure water main, which would enable workshops to operate machinery. The high-pressure water would be applied "to
7056-488: The mid-1700s, French engineer Bernard Forest de Bélidor published Architecture Hydraulique , which described vertical- and horizontal-axis hydraulic machines, and in 1771 Richard Arkwright 's combination of water power , the water frame , and continuous production played a significant part in the development of the factory system, with modern employment practices. In the 1840s, hydraulic power networks were developed to generate and transmit hydro power to end users. By
7154-651: The natural ecology of the river involved, affecting habitats and ecosystems, and siltation and erosion patterns. While dams can ameliorate the risks of flooding, dam failure can be catastrophic. In 2021, global installed hydropower electrical capacity reached almost 1,400 GW, the highest among all renewable energy technologies. Hydroelectricity plays a leading role in countries like Brazil, Norway and China. but there are geographical limits and environmental issues. Tidal power can be used in coastal regions. China added 24 GW in 2022, accounting for nearly three-quarters of global hydropower capacity additions. Europe added 2 GW,
7252-442: The need for a filtration plant. At this time two pumpsets were in use, and a third was being installed. Pressure was maintained by two accumulators, each with an 18-inch (460 mm) diameter piston with a stroke of 20 feet (6.1 m). The Practical Engineer quoted the pressure as 75 pounds per square inch (5.2 bar), but this is unlikely to be correct by comparison with other systems. A second pumping station at Grafton Street
7350-478: The number of men required to operate them from twelve to four. Each of these schemes was for a single customer, and the application of hydraulic power more generally required a new model. The first practical installation which supplied hydraulic power to the public was in Kingston upon Hull , in England. The Hull Hydraulic Power Company began operation in 1876. They had 2.5 miles (4.0 km) of pipes, which were up to 6 inches (150 mm) in diameter, and ran along
7448-633: The plant site. Generation of hydroelectric power changes the downstream river environment. Water exiting a turbine usually contains very little suspended sediment, which can lead to scouring of river beds and loss of riverbanks. The turbines also will kill large portions of the fauna passing through, for instance 70% of the eel passing a turbine will perish immediately. Since turbine gates are often opened intermittently, rapid or even daily fluctuations in river flow are observed. Drought and seasonal changes in rainfall can severely limit hydropower. Water may also be lost by evaporation. When water flows it has
7546-541: The pressure and flow, rather than storing power. While the network supplied lifts, cranes and dockgates, it also powered the cabaret platform at the Savoy Hotel, and from 1937, the 720-tonne three-section central floor at the Earls Court Exhibition Centre , which could be raised or lowered relative to the main floor to convert between a swimming pool and an exhibition hall. The London system contracted during
7644-450: The rainfall regime, could reduce total energy production by 7% annually by the end of the century. Lower positive impacts are found in the tropical regions. In lowland rainforest areas, where inundation of a part of the forest is necessary, it has been noted that the reservoirs of power plants produce substantial amounts of methane . This is due to plant material in flooded areas decaying in an anaerobic environment and forming methane,
7742-646: The supply. They maintained 184 miles (296 km) of mains at 700 psi (48 bar), which covered an area reaching Pentonville in the north, Limehouse in the east, Nine Elms and Bermondsey in the south and Earls Court and Notting Hill in the west. Five pumping stations kept the mains pressurised, assisted by accumulators. The original station was at Falcon Wharf, Bankside, but this was replaced by four stations at Wapping, Rotherhithe, Grosvenor Road in Pimlico and City Road in Clerkenwell. A fifth station at East India Docks
7840-781: The time of its installation, such a scheme seemed like "a leap in the dark", according to R. H. Tweddell writing in 1895, but despite a lack of enthusiasm for the scheme, Ellington pushed ahead and used it as a test bed for both the mechanical and the commercial aspects of the idea. He was eventually involved on some level in most of the hydraulic power networks of Britain. The success of such systems led to them being installed in places as far away as Antwerp in Belgium, Melbourne and Sydney in Australia, and Buenos Aires in Argentina. Independent hydraulic power networks were also installed at Hull's docks - both
7938-425: The water was supplied at a pressure of 2 to 3 bars (29 to 44 psi). Due to increased demand, a new pumping plant was installed, which started operation in 1886. The pumps were driven by Jonval turbines using the water power of the river Rhône . This structure was called Usine des Forces Motrices and was one of the largest structures for generation and distribution of power at the time of construction. By 1897
8036-577: The west bank of the River Hull from Sculcoates bridge to its junction with the Humber . The pumping station was near the north end of the pipeline, on Machell Street, near the disused Scott Street bascule bridge, which was powered hydraulically. There was an accumulator at Machell Street, and another one much nearer the Humber, on the corner of Grimsby Lane. Special provision was made where the pressure main passed under
8134-524: The world are hydroelectric power stations, with some hydroelectric facilities capable of generating more than double the installed capacities of the current largest nuclear power stations . Although no official definition exists for the capacity range of large hydroelectric power stations, facilities from over a few hundred megawatts are generally considered large hydroelectric facilities. Currently, only seven facilities over 10 GW ( 10,000 MW ) are in operation worldwide, see table below. Small hydro
8232-539: The world. The classification of hydropower plants starts with two top-level categories: The classification of a plant as an SHP or LHP is primarily based on its nameplate capacity , the threshold varies by the country, but in any case a plant with the capacity of 50 MW or more is considered an LHP. As an example, for China, SHP power is below 25 MW, for India - below 15 MW, most of Europe - below 10 MW. The SHP and LHP categories are further subdivided into many subcategories that are not mutually exclusive. For example,
8330-540: Was added in 1901, and in 1902, 102 million gallons (454 megalitres) of pressurised water were used by customers. The system was operated as a commercial enterprise until 1925, after which the business and its assets reverted to the City of Melbourne, as specified by the original act. One of the early improvements made by the City Council was to consolidate the system. The steam pumps were replaced by new electric pumps, located in
8428-573: Was allowed to provide irrigation and power to citizens (in addition to aluminium power) after the war. In Suriname , the Brokopondo Reservoir was constructed to provide electricity for the Alcoa aluminium industry. New Zealand 's Manapouri Power Station was constructed to supply electricity to the aluminium smelter at Tiwai Point . Since hydroelectric dams do not use fuel, power generation does not produce carbon dioxide . While carbon dioxide
8526-632: Was an economical use of hydraulic power, although tests conducted at his works at Chester in October 1894 showed that efficiencies of 59 per cent could be achieved using a Pelton wheel directly coupled to a dynamo. Two major systems were built in Australia. The first was in Melbourne , where the Melbourne Hydraulic Power Company began operating in July 1889. The company was authorised by an Act of
8624-560: Was an offshoot of the London-based General Hydraulic Power Company, and was authorised by acts of Parliament obtained in 1884 and 1887. By 1890, some 16 miles (26 km) of mains had been installed, supplied by a pumping station at Athol Street, on the bank of the Leeds and Liverpool Canal . Although water was originally taken from the canal, cleaner water supplied by Liverpool Corporation was in use by 1890, removing
8722-440: Was built next to the powerhouse, which generated 110 V DC with a maximum power of 800 hp (600 kW) and an AC network with a maximum power of 600 hp (450 kW). The generators were driven by a water turbine supplied from the hydraulic power network. The hydraulic power network was not in competition with the electric power supply, but was seen as a supplement to it, and continued to supply power to many customer until
8820-468: Was built on the east side of Gloucester Street, by Manchester Oxford Road railway station . It was later supplemented by stations at Water Street and Pott Street, the latter now under the car parks of the Central Retail Park. At its peak in the 1930s, the system consisted on 35 miles (56 km) of pipes, which were connected to 2,400 machines, most of which were used for baling cotton. The system
8918-568: Was how later hydraulic power systems worked. In Newcastle upon Tyne , a solicitor called William Armstrong , who had been experimenting with water-powered machines, was working for a firm of solicitors who were appointed to act on behalf of the Whittle Dene Water Company. The water company had been set up to supply Newcastle with drinking water, and Armstrong was appointed secretary at the first meeting of shareholders. Soon afterwards, he wrote to Newcastle Town Council, suggesting that
9016-587: Was operational by 1909. The system ceased operation in 1971. Birmingham obtained its system in 1891, when the Dalton Street hydraulic station opened. In an unusual move, J. W. Gray, the Water Department engineer for the city, had been laying pressure mains beneath the streets for some years, anticipating the need for such a system. The hydraulic station used Otto 'Silent' type gas engines, and had two accumulators, with an 18-inch (460 mm) diameter piston,
9114-445: Was originally operated by the Port of London Authority , but was taken over and connected to the system. The stations used steam engines until 1953, when Grosvenor Road station was converted to use electric motors, and following the success of this project, the other four were also converted. The electric motors allowed much smaller accumulators to be used, since they were then only controlling
9212-521: Was shut down in 1964. All of the British systems were designed to provide power for intermittent processes, such as the operation of dock gates or cranes. The system installed at Antwerp was somewhat different, in that its primary purpose was the production of electricity for lighting. It was commissioned in 1894, and used pumping engines producing a total of 1,000 hp (750 kW) to supply water at 750 psi (52 bar). Ellington, writing in 1895, stated that he found it difficult to see that this
9310-431: Was shut down in 1972. In Glasgow, the pumping station was at the junction of High Street and Rottenrow. By 1899, it was supplying power to 348 machines, and another 39 were in the process of being completed. The pipes were 7 inches (180 mm) in diameter, and there were around 30 miles (48 km) of them by 1909, when 202,141 imperial gallons (918.95 m ) of high pressure water were supplied to customers. The system
9408-513: Was situated in the Darling Harbour district, and the original steam engines were replaced by three electric motors driving centrifugal pumps in 1952. The scheme remained in private ownership until its demise in 1975, and the pumping station has since been re-used as a tavern. Ellington's system in Buenos Aires was designed to operate a sewage pumping scheme in the city. Geneva created
9506-591: Was the Sydney and Suburbs Hydraulic Power Company, later shortened to the Sydney Hydraulic Power Company. Pressure mains were either of 4-inch (100 mm) or 6-inch (150 mm) diameter, and at its peak, there were around 50 miles (80 km) of mains, covering an area between Pyrmont , Woolloomooloo , and Broadway . In 1919, most of the 2369 lifts in the metropolitan area were hydraulically operated. The pumping station, together with two accumulators,
9604-476: Was used for powering 130 Schmid type water engines with a gross power of 230 hp (170 kW). The high pressure network had an operating pressure of 14 bars (200 psi) bar and had a total length of 58 miles (93 km). It was used to power 207 turbines and motors, as well as elevator drives, and had a gross power of 3,000 hp (2,200 kW). Many turbines were used for driving generators for electric lighting. In 1887 an electricity generation plant
#498501